Procurement of good governance as a strategic tool for achieving value for money in public construction projects

Atupakisye Mwakolo (Department of Procurement and supply Management, College of Business Education, Mbeya Campus, Mbeya, Tanzania)
Meshack Siwandeti (Department of Procurement and supply Management, College of Business Education, Mwanza Campus, Mwanza, Tanzania)
Leticia Mahuwi (Department of Procurement and supply Management, College of Business Education, Mbeya Campus, Mbeya, Tanzania)
Baraka Israel (Department of Procurement and supply Management, College of Business Education, Mbeya Campus, Mbeya, Tanzania)

LBS Journal of Management & Research

ISSN: 0972-8031

Article publication date: 19 April 2024

193

Abstract

Purpose

The study aims to explore the role of procurement of good governance (PGG) on value for money (VfM) achievement in public construction projects. By investigating various dimensions of PGG, including transparency, accountability, competition and integrity, this study provides insights into how these factors contribute to the successful achievement of VfM outcomes in public construction projects.

Design/methodology/approach

The data were sourced from 203 construction project practitioners from 24 selected procuring entities in Tanzania using a census approach and a cross-sectional questionnaire survey. Confirmatory factor analysis (CFA) and structural equation modelling (SEM) were used for data analysis.

Findings

The findings of the study revealed a positive and significant impact of various dimensions of PGG on VfM. Specifically, transparency, accountability, competition and integrity were positively and significantly related to VfM, with p-values <0.001. Based on the study findings, we conclude that PGG is an important predictor of VfM achievement in public construction projects.

Practical implications

The study offers policy implications for streamlined PGG and VfM achievement in public construction projects. It is suggested that procuring entities can enhance VfM by enforcing compliance with the principles of PGG throughout the entirety of construction projects. In this case, streamlined legislative frameworks and control mechanisms are crucial components that could enhance PGG and the achievement of VfM.

Originality/value

This study contributes to the academic literature on the strategic role of PGG in enhancing VfM achievement. This is one of the research domains, which has not been adequately researched, particularly in Tanzania’s context. In addition, the study provides valuable insights to policymakers, practitioners and stakeholders involved in public construction projects to improve project outcomes and resource allocation.

Keywords

Citation

Mwakolo, A., Siwandeti, M., Mahuwi, L. and Israel, B. (2024), "Procurement of good governance as a strategic tool for achieving value for money in public construction projects", LBS Journal of Management & Research, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/LBSJMR-08-2023-0027

Publisher

:

Emerald Publishing Limited

Copyright © 2024, Atupakisye Mwakolo, Meshack Siwandeti, Leticia Mahuwi and Baraka Israel

License

Published in LBS Journal of Management & Research. Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode


1. Introduction

Public construction projects play a crucial role in the development and growth of societies and governments by supporting socio-economic activities and public welfare. It encompasses a wide range of activities, including planning, designing, renovating and erecting tangible infrastructures such as roads, airports, bridges, schools, hospitals, waterway systems and public buildings (Bajjou & Chafi, 2020; Israel, 2023). Approximately 90% of socio-economic activities, public welfare and livelihoods, such as trade, communication, shelter and access to health and education facilities, heavily rely on the effectiveness of construction projects (World Bank, 2020; Heravi & Mohammadian, 2021). Consequently, construction projects have received significant attention in today's business, socio-economic and legal environments due to their importance to societies and the complexities they face. From a socio-economic perspective, it is estimated that construction projects consume around 20% to 30% of government budgets, employ two million people worldwide and account for 8% of the global gross domestic product (GDP) World Bank (2020), (United Republic of Tanzania (URT), 2021).

The primary objective of public construction projects is to plan and execute them in a manner that maximises economic benefits for the government and meets the requirements of users. It stems from the desire to achieve greater economy, efficiency and effectiveness, which serve as the proxies of value for money (VfM) (Obieje, 2019; Olatunji et al., 2017; Staples & Dalrymple, 2012). Essentially, procuring entities (PEs) evaluate VfM in construction projects based on these three indicators. The economy gauges the cost-effectiveness of project acquisition. Projects that are planned and executed within the estimated budget and at the lowest possible costs fulfil the economic aspect of VfM (McArdle & Gunning, 2018; Sayi & Monko, 2022). Efficiency measures the overall benefits obtained from projects in relation to resources invested, compliance with quality standards, sustainability and timely delivery. Effectiveness assesses the extent to which PEs have achieved the predetermined objectives of the projects. Given the significant amount of funds invested in public construction projects and the goal of achieving VfM, many governments and international organisations have established stringent principles and regulations that advocate for procurement of good governance (PGG) and VfM achievement. PGG encompasses the principles, regulations and mechanisms that govern the conduct of public procurement, including the planning, tendering, contract awarding and monitoring (Shakya, 2015; Kwofie, Ellis, & Opoku, 2021; Siwandeti, Mahuwi, & Israel, 2023).

In some instances and countries, procurement of construction projects is governed by the United Nations Commission on International Trade Law (UNCITRAL) model law, as well as the guidelines provided by the World Bank and the African Development Bank for the procurement of goods, works, consultancy and non-consulting services (World Bank, 2014; African Development Bank (AfDB), 2012). Most importantly, African countries have enacted and revised Public Procurement Acts (PPA) that outline the principles and regulations that govern public-funded projects. These frameworks establish the guidelines and best practices for PGG, aiming to prevent malpractices and achieve VfM. Amongst others, the frameworks advocate for transparency, competitive bidding, fairness, accountability, integrity, anti-corruption measures and professionalism as the key principles of PGG that enhance VfM in the public bidding process (World Bank, 2014; AfDB, 2012). Studies regard PGG as the principal pillar through which PEs can improve project performance and nurture VfM (Staples & Dalrymple, 2012; Oke, Aigbavboa, & Tong, 2018; Gransberg, Molenaar, Scott, & Smith, 2007). To attain these goals, countries like Kenya, Uganda, South Africa and Ghana, amongst others, have established public procurement oversight authorities with responsibilities to oversee and monitor compliance with the principles of PGG and VfM in PEs.

Notwithstanding the measures and frameworks in place, the planning, procurement, execution and delivery of public construction projects across the globe are not without flaws. Achieving VfM remains a significant challenge for many governments (World Bank, 2020; Matto, Ame, & Nsimbila, 2021; Sayi & Monko, 2022). Governments are striving to reduce costs and increase efficiency and effectiveness. Statistics reveal that about 50% of global construction projects experience cost and time overruns (World Bank, 2020; Israel, 2023; Heravi & Mohammadian, 2021). This issue is particularly pronounced in Sub-Saharan Africa, where 80% of construction projects fail to achieve VfM, encountering delays and cost overruns (World Bank, 2020). Studies conducted by Idrees and Shafiq (2021), Israel (2022) and Kwofie et al. (2021) revealed corrupt practices as the main obstacle hindering PEs from realising VfM in public construction projects. This results in PEs losing approximately 20% to 30% of the project value (World Bank, 2020). Additionally, Obieje (2019) and Sayi and Monko (2022) highlighted a lack of professionalism amongst project practitioners, inappropriate procurement methods and the utilisation of unskilled contractors, sub-contractors and consultants as the prime deficiencies that affect VfM achievement in construction projects. These contribute to delays and cost overruns, thus hindering the attainment of VfM.

In the context of Tanzania, like other Sub-Saharan African countries, the construction sector faces numerous complexities and deficiencies that hinder the realisation of VfM. Issues of efficiency, quality, time and cost overruns remain critical problems (Israel, 2023; Matto, 2023). Evidence reveals that more than 47.3% of construction projects experience time and cost overruns (World Bank, 2020; URT, 2021). In particular, studies by Matto et al. (2021) and Mchopa (2015) reported inefficient contract management, corruption, nepotism, conflicting goals amongst practitioners and non-compliance with contractual terms as the root causes of inefficiency, delays, quality and cost issues in public construction projects. However, there is insufficient literature providing a comprehensive overview of the role of PGG on VfM achievement. Previous studies have addressed the challenges and deficiencies in project management (Pastory, 2019; Matto, 2023; Israel, 2022), the causes of cost and time overruns (Kavishe, Jefferson, & Chileshe, 2018; Manege & Kennedy, 2020) and the integration of contract management and VfM (Mchopa, 2015; Matto, 2023). To bridge this gap, the current study employs governance theory to investigate whether PGG helps PEs achieve VfM in the context of Tanzania’s public construction projects. The main question of the study is:

RQ.

Does PGG significantly affect the achievement of VfM?

By addressing the above research question, the study operationalises the role of PGG in the context of construction projects. Delving into the intricate fabric of PGG, the study goes beyond the confines of traditional methods, focussing on its inherent potential as a strategic tool and paves the way for conceptual frameworks that harmonise ethical governance with fiscal policies. The first section of this paper is structured as its introduction, providing an overview of the study. Section 2 provides a summary of literature, encompassing both theoretical and empirical viewpoints that form the basis for hypotheses development. The methodology is outlined in Section 3. The analysis results, encompassing the model's fit and hypotheses testing are presented in Section 4, which is followed by a discussion of findings in Section 5. Section 6 delves into the conclusion, study implications, limitations and suggestions for future studies.

2. Literature review and hypothesis development

2.1 The governance theory

In line with previous literature (Panga, 2021; Shakya, 2015; Anderson, Kovacic, & Müller, 2011; Stoker, 2006), we adopt the governance theory to assess the role of PGG on VfM achievement in public construction projects. The governance theory, established by the World Bank, sets basic principle for governments to achieve efficiency, improve performance and enhance prosperity in public service delivery (Williams & Young, 1994). These principles include transparency, responsiveness, inclusiveness, accountability, efficiency and economy. Additionally, the International Monetary Fund (IMF, 2022) and the United Nations Development Programme (UNDP, 2007) extend the principles of good governance to include integrity, the rule of law and ethical conduct. These principles provide a framework for the effective utilisation of public resources and promote good practices. The governance theory considers these principles as essential elements through which governments and PEs can enhance prosperity and improve performance (Bevir, 2011; Shakya, 2015; Glas, Gaus, & Ebig, 2018; Panga, 2021).

The performance of construction projects is assessed based on cost-effectiveness over their entire lifecycle, quality standards and timely delivery, all of which contribute to the measurement of VfM (Sayi & Monko, 2022; McArdle & Gunning, 2018). To achieve these objectives, PEs require robust principles, regulatory frameworks and enforcement mechanisms to govern and monitor the procurement of public projects. The current study assesses the theoretical implications of the governance theory in enhancing VfM achievement in public construction projects. The assessment is based on the fundamental principles of PGG, namely accountability, transparency, competition and integrity. Based on this, the study asserts that streamlined PGG can help PEs achieve VfM. This is attributed to the fact that PGG promotes anti-corruption, transparency, responsibility and accountability amongst procurement practitioners, which, according to Botlhale (2017) and Marinelli and Antoniou (2020), are important drivers of VfM.

2.2 Procurement of public construction project and VfM issues in Tanzania

The procurement of public-funded projects in Tanzania is governed by the PPA (CAP. 410 R.E. 2016) (URT, 2011) and its associated procurement regulations (URT, 2013) (as amended in 2016). These legislative instruments establish the principles of PGG, aiming to achieve VfM by promoting transparency, competitive bidding, fairness, accountability, integrity and ethical practices. Essentially, these frameworks emphasise the timely planning, execution and delivery of high-quality projects in a cost-effective manner. Aligned with these objectives, Part III of the public procurement regulations outlines the procedures and requirements for hiring contractors and consultants, as well as the management and execution of construction projects. Amongst other stipulations, the regulations emphasise the importance of selecting and employing capable and qualified contractors and consultants, along with using appropriate procurement methods as prerequisites for achieving VfM (URT, 2013). Entities such as the Tanzania Rural and Urban Roads Agency (TARURA), Tanzania Building Agency (TBA), the Tanzania National Roads Agency (TANROADS) and the Contractors Registration Board (CRB) play crucial roles in planning, executing and overseeing the implementation, rehabilitation and maintenance of construction projects, with the primary focus on achieving VfM (URT, 2021; URT, 2013).

The legislative instruments and oversight entities in place aim to ensure that public-funded projects are planned, implemented and delivered on time, achieving better quality and cost-effectiveness, whilst also considering sustainability, innovation and stakeholder satisfaction (Israel, 2023; Glas et al., 2018; Brito & Miguel, 2017). These goals are integral to VfM achievement and must be considered when evaluating the success of construction projects (Ibrahim, Bawole, Obuobisa-Darko, Abubakar, & Kumasey, 2017; Nyanyofio, Domfeh, Buabeng, Maloreh-Nyamekye, & Appiah-Agyekum, 2022). In particular, the Public Procurement Regulatory Authority (PPRA) is mandated with important roles to monitor compliance with the principles of PGG and report whether the best results and highly qualified outcomes are obtained on time and at effective costs (URT, 2013). In the context of public construction projects, VfM is assessed throughout the project's planning, design, construction and closeout phases. Literature establishes that PEs can successfully achieve VfM by, amongst other strategies, complying with the fundamental principles of PGG (Changalima, Ismail, & Mwaiseje, 2022; Mrope, Namusonge, & Iravo, 2017). PGG minimises the risks of corrupt practices, increases efficiency and enhances effectiveness in procurement proceedings (Botlhale, 2017; Nyanyofio et al., 2022).

2.3 Hypotheses development

2.3.1 Transparency and VfM achievement

In the context of public procurement, transparency refers to the means and processes through which procurement contracts are defined, advertised, awarded and managed. It involves effective communication and openness between the PEs and bidders (URT, 2013; World Bank, 2014; Brito & Miguel, 2017). Procurement regulations stipulate that all aspects related to procurement procedures, tender advertisements, timelines, evaluation criteria and award decisions should be conducted and publicly maintained by the PEs to enhance transparency (URT, 2013). Moreover, empirical studies consider e-procurement as a crucial foundation of transparency through which PEs can bolster effective and efficient resource utilisation (Bauhr, Czibik, Licht, & Fazekas, 2020; Harnovinsah, Al-Hakim, Erlina, & Muda, 2020). Studies by Sayi and Monko (2022), Israel, Mchopa, Mwaiseje and Mashene (2019) and Sama (2022) have reported positive and significant effects of transparency on the performance of PEs in terms of cost-effectiveness, quality and timely delivery. This is attributed to the fact that transparency promotes competition and accountability in public procurement processes. Well-implemented transparency-related practices enable PEs to select and engage qualified and competent bidders who can deliver projects within the agreed time, specifications and budget (Heald, 2018; Asuquo, Lashinde, & Adu, 2021). Based on these perspectives, the following hypothesis is proposed:

H1.

Transparency is positively related to VfM achievement.

2.3.2 Accountability and VfM achievement

Accountability pertains to how procurement practitioners exercise their power and act in accordance with specified legislation and codes of conduct (Harnovinsah et al., 2020; Ibrahim et al., 2017). Mrope et al. (2017) further expand the concept of accountability to include how public officials accept responsibility and liability for their actions. It has been argued that a commitment to accepting liability and adhering to the existing legislation is crucial for improved procurement performance (Nyanyofio et al., 2022; Obieje, 2019). In this regard, the achievement of VfM in public-funded projects requires procurement practitioners to act in the public interest and comply with procurement regulations. Yet, literature reveals that public-funded projects experience delays, cost overruns and poor quality due to a lack of accountability amongst public buyers during procurement processes (Marinelli & Antoniou, 2020; Johnson & Babu, 2020; Gomes, Small, & Yasin, 2019). Conversely, PEs that prioritise accountability are more likely to attain cost-effectiveness and improve quality and time performance (Mrope et al., 2017; Obieje, 2019). Accountability governs ethical behaviour of procurement practitioners, thereby serving as a critical driver of organisational performance and VfM achievement. It is therefore hypothesised that:

H2.

Accountability is positively related to VfM achievement.

2.3.3 Competition and VfM achievement

Accordingly, literature asserts that PEs can enhance VfM achievement in public construction projects by enhancing the competitive bidding process (Panga, 2021; Anderson et al., 2011). Public procurement regulations and guidelines require PEs to use competitive tendering as the default method in public procurement, with equal participation and treatment of bidders in pre-qualification and post-qualification processes (URT, 2013; Mahuwi & Israel, 2023). Moreover, the regulations and guidelines prohibit dividing contracts to circumvent thresholds for competitive tenders. The current study suggests that competitive bidding can significantly contribute to the achievement of VfM. In line with this perspective, studies by Panga (2021) and Sama (2022) revealed a positive and significant relationship between competitive bidding and organisational performance. This interplay can occur because competitive bidding maximises competition in the bidding process, enabling PEs to select the best-priced and highly qualified bidders. Based on these arguments, the study hypothesises that:

H3.

Competition is positively related to VfM achievement.

2.3.4 Integrity and VfM achievement

Integrity refers to strong moral principles and honesty exhibited by procurement practitioners in their dealings with bidders (Bosio, Djankov, Glaeser, & Shleifer, 2022; Kafimbou, 2019). It encompasses practices such as the prompt selection of bidders, preservation of unchanged bid evaluation and selection criteria, specifications and processes after bids are opened and compliance with pre-set contractual terms and conditions (Bosio et al., 2022). Several studies have reported a positive and significant relationship between integrity in public procurement and organisational performance (Hsueh, Bretschneider, Stritch, & Darnall, 2020; Obieje, 2019; Olatunji et al., 2017; Marinelli & Antoniou, 2020). Conversely, the lack of integrity and non-compliance with procurement principles and contractual terms have been reported to have a negative effect on organisations' performance (Kafimbou, 2019; Gomes et al., 2019; Ibrahim et al., 2017). Maintaining integrity fosters good relationships and harmony between PEs and service providers during contract implementation, thereby increasing efficiency. Increased efficiency subsequently helps PEs achieve VfM by minimising operational costs and improving the quality and timely delivery of projects (Brito & Miguel, 2017). It is thus hypothesising that:

H4.

Integrity is positively related to VfM achievement.

2.4 Research gap

Despite the growing recognition of the importance of procurement in promoting good governance, a notable gap exists in the literature regarding the specific influence of PGG in achieving VfM within the unique context of Tanzania's public construction sector. Previous research often focusses on addressing the challenges and deficiencies that hinder PEs from achieving VfM (Pastory, 2019; Matto, 2023; Israel, 2022), the drivers of cost and time overruns in construction projects (Kavishe et al., 2018; Manege & Kennedy, 2020; Israel, 2023) and the perceived benefits of regulatory compliance in public bidding process (Changalima et al., 2022; Sama, 2022; Panga, 2021). Understanding the role of PGG in achieving VfM is essential for devising practical strategies for effective implementation and delivery of public construction projects. Therefore, bridging this gap is vital for providing actionable insights that can guide policymakers, practitioners and stakeholders in developing and refining strategies that align with the unique dynamics of the Tanzanian public construction sector.

2.5 The conceptual framework

Figure 1 is the conceptual framework of this study which demonstrates the relationships between PGG and VfM achievement in public construction projects. The framework was developed based on a literature review and the formulated four hypotheses. The conceptual framework hypothesises that the underlying principles of PGG (H1, H2, H3 and H4) are positively related to VfM.

3. Methodology

3.1 Research design and sampling

A quantitative research approach and cross-sectional research design were adopted for this study. The approach fits well with the study because we sought to establish a statistical link between the explanatory and outcome variables (Dominowski, 1980). On the other hand, data was collected at a single point in time from the targeted population to describe the status of PGG and VfM achievement, hence forming the basis for a cross-sectional research design (Saunders, Lewis, & Thornhill, 2019). The target population for this study consisted of 256 construction project practitioners from 24 PEs across four regions in Tanzania, namely Mbeya, Iringa, Dodoma and Songwe. These included heads of procurement units, project managers, heads of user departments, accounting officers, heads of finance units, project consultants, chairmen of the tender boards and auditors. Participants were chosen based on their rational roles in planning, execution and overseeing compliance with PGG in public construction projects (Kwofie et al., 2021; Matto et al., 2021). The basis for selecting the 24 PEs is that they were identified by the Controller Auditor General (CAG) as having implemented construction projects with indicators suggesting the likelihood of achieving VfM, such as cost-effectiveness, timely delivery and quality standards (URT, 2021). Due to the relatively small size of the target population, a census approach was utilised, including the entire population as the unit of analysis (Israel, 1992).

3.2 Data collection and sample size

The study collected primary quantitative data for analysis. A self-administered questionnaire containing structured questions was used to collect the data and test the relevance of governance theory in assessing the role of PGG on VfM. Initially, an extensive literature review was conducted to identify the constructs of PGG and VfM, which were then used to construct a questionnaire survey. To ensure content validity before data collection, the questionnaire was shared with five public procurement practitioners who were not part of the study population. Changes were appropriately incorporated into the questionnaire to enhance its quality and clarity. Subsequently, questionnaires were distributed to the targeted 256 construction project practitioners who had first-hand knowledge of PGG and VfM achievement in the identified 24 PEs. However, out of the 256 questionnaires distributed, only 203 valid responses were obtained, accounting for approximately a 79.3% response rate. The final sample size of 203 was deemed sufficient for conducting confirmatory factor analysis (CFA) and structural equation modelling (SEM), as both techniques, according to Wolf, Harrington, Clark and Miller (2013) and MacKinnon, Lockwood, Hoffman, West and Sheets (2002), require a minimum sample size of 200 or more. A structured questionnaire survey was preferred in this study to capitalise on the advantages of minimising biases in data collection whilst covering a large number of respondents within a short time (Saunders et al., 2019).

3.3 Measurement of the study variables

The questionnaire survey developed for this study had four constructs that reflected the aspects of PGG and VfM. The four constructs were transparency, accountability, competition and integrity, as hypothesised in Figure 1. Transparency and integrity were measured using five items each, whilst competition and accountability were measured using four items each. The constructs and items related to PGG were adopted and modified from Bosio et al. (2022), Israel et al. (2019) and Bevir (2011). The outcome variable (VfM) was measured using three items of Panga (2021), McArdle and Gunning (2018) and Olatunji et al. (2017). For each statement within a construct, respondents were asked to indicate the potential influence of PGG on VfM achievement, based on their experience in construction projects. Each item was measured using a 5-point Likert scale, ranging from “1 = not at all” to “5 = very great extent.”

3.4 Data analysis

SEM (AMOS 23.0) was employed for data analysis. SEM enables the examination of relationships between one or more discrete or continuous constructs and outcome variables (Fan et al., 2016; Hair, Ringle, & Sarstedt, 2013). CFA was conducted beforehand to investigate the underlying data structure and unidimensionality of the constructs based on SEM's measurement model. The patterns of latent constructs and observed variables for transparency, accountability, competition, integrity and VfM in public construction projects were depicted. Through CFA, factor loadings were utilised to assess the model fitting indices, reliability and validity of the data. Finally, SEM employed regression analysis to examine the hypothesised relationships between PGG and VfM achievement.

4. Research findings

4.1 Characteristics of respondents

Table 1 provides demographic information about the respondents included in this study. The majority of respondents were auditors (23.15%, n = 47), followed by project consultants and chairmen of tender boards (11.82%, n = 24). Males accounted for the appropriate large number of respondents in this study (65.52%, n = 133), compared to 34.48% (n = 70) who were female. Again, 31.53% (n = 64) of the sampled respondents had an average age of 31–40 years, followed by those aged 41–50 years (28.57%, n = 58). Statistics further show that the working experience of respondents included in the study mostly ranged between 5 and more than 10 years (34.98%), followed by 22.17% with work experience of 10 to 15 years. Lastly, 44.83% (n = 91) of the participants held a first degree, whilst 38.42% (n = 78) had postgraduate education. These statistics indicate that respondents were sampled from diverse working positions, possessing adequate education and working experience to respond to questions related to PGG and VfM in the context of construction projects.

4.2 Reliability and validity

The reliability and validity of the research tools and data were assessed using composite reliability (CR) and Cronbach's alpha (α). According to Hair et al. (2013) and Henseler, Ringle and Sarstedt (2015), Cronbach's alpha and CR values ≥ 0.70 are considered acceptable. The results of CFA in Table 2 reveal that the values of Cronbach's alpha and CR for all constructs are above the recommended threshold of 0.7, hence confirming the attainment of reliability and validity of the research tools. Also, the average variance extracted (AVE) was utilised to evaluate the model's discriminant and convergent validity, following the Fornell–Lacker criterion. An AVE value of ≥0.50 is considered to be good (Hair et al., 2013). Table 2 further demonstrates that convergent validity was achieved with an AVE value of ≥0.50. After convergent validity, the discriminant validity which establishes how each construct is distinct from the others in terms of measurement scales was also tested. Discriminant validity is confirmed when the square root of the AVE is greater than the correlation value of other constructs in the model (Henseler et al., 2015). The results depicted in Table 3 affirm the attainment of discriminant validity.

4.3 Assessment of measurement model

The next step involved testing whether the structural model provided a good fit for examining the relationship between PGG and VfM. Initially, the model did not meet the criteria for a good fit. The obtained indices from the initial model were as follows: χ2 = 760.626 with a degree of freedom (df) = 179 at p < 0.01, χ2/df = 4.249, goodness-of-fit index (GFI) = 0.818, incremental fit index (IFI) = 0.838, comparative fit index (CFI) = 0.837, Tucker–Lewis index (TLI) = 0.809, root mean square error of approximation (RMSEA) = 0.109 and PClose = 0.000. This lack of fit was attributed to two items, Acc1 and integ5, which had factor loadings below 0.7, as indicated by asterisks in Table 2. The two items were removed from the model to improve its strength. Additionally, covariance of error terms based on modification indices (MI > 20) was introduced. The revised measurement model demonstrated a good fit with the following indices: χ2 = 226.824, df = 141 at p < 0.01, χ2/df = 1.609, GFI = 0.917, IFI = 0.972, CFI = 0.971, TLI = 0.965, RMSEA = 0.047 and PClose = 0.646. The results of the measurement model extracted in this study are presented in Figure 2 and Table 2.

4.4 Structural model and hypothesis testing

After confirming that the measurement model (Figure 2) fit well with the data, the next step was to run the structural model and examine the relationships between the endogenous and exogenous variables (Figure 3). The model fit indices for the structural model were found to be within the recommended threshold: χ2 = 354.413, df = 147, p < 0.01, χ2/df = 2.411, GFI = 0.913, CFI = 0.931, IFI = 0.932, TLI = 0.920 and RMSEA = 0.072. Specifically, the analysis of the structural model provided support for Hypothesis 1, which states that H1: transparency is positively related to VfM achievement” with β = 0.399 and p < 0.001. This finding suggests that transparency-related practices play a critical and significant role in supporting VfM achievement in public construction projects. This means that if PEs uphold transparency by one unit, VfM increases by 39.9%. Also, accountability emerged as a crucial and significant principle of PGG that positively contributes to VfM achievement in public construction projects, as evidenced by β = 0.125 and p < 0.001. Thus, Hypothesis 2, which states that H2: accountability is positively related to VfM achievement”, was supported. Therefore, a one-unit increase in accountability leads to a 12.5% increase in VfM. Again, H3, which hypothesised a positive relationship between competition and VfM was also supported (β = 0.230, p < 0.001). This imply that for every unit increase in competition, VfM goes up by 23.0%. Finally, H4, which states that “H4: integrity is positively related to VfM achievement” was also supported as the results in Table 4 show a positive and significant relationship between integrity and VfM (β = 0.245, p < 0.001). This implies that holding other variables constant at zero, a one-unit increase in integrity is associated with a 24.5% increase in VfM.

5. Discussions

The results of the study confirmed the proposed four hypotheses. Amongst others, the study findings supported the first hypothesis, which establishes a positive link between transparency and VfM achievement. Consistent with Manege and Kennedy’s (2020) and Heald’s (2018) findings, the study reveals that transparency-related practices such as the exclusive use of e-procurement systems in the bidding process, ensuring the timely availability of annual procurement plans and providing equal opportunities to bidders, have a higher likelihood in supporting VfM achievement in public construction projects. This is due to the fact that transparency discourages corrupt-related practices, thereby promoting accountability and fairness, which are essential drivers of VfM. Nevertheless, these findings align with the assumptions of governance theory (Williams & Young, 1994; Glas et al., 2018), as well as the arguments that transparent processes lead to better-informed procurement stakeholders and increased competition amongst contractors, all of which contribute to achieving better performance and VfM achievement (Bauhr et al., 2020; Brito & Miguel, 2017; Sayi & Monko, 2022).

Second, the findings demonstrated a positive and statistically significant effect of accountability on VfM. This finding corroborates with the assumptions of governance theory and the arguments presented by Olatunji et al. (2017) and Harnovinsah et al. (2020), which stress that well-established accountability-related practices and mechanisms have a significant and positive impact on service delivery and overall VfM achievement. These findings ascertain that robust internal and external control mechanisms and systems, coupled with clear project oversight, reporting, performance evaluation, rewarding and punishing of procurement malpractices, foster accountability amongst procurement officials. This, in turn, enhances efficiency, effectiveness and compliance with procurement laws and procedures, which, according to the governance theory (Glas et al., 2018; Williams & Young, 1994), as well as the findings of Oke et al. (2018) and Gransberg et al. (2007), are important factors for achieving VfM in public construction projects. Accountability enables PEs and procurement officials to steer clear of corruption and procurement malpractices, which act as obstacles to VfM achievement in public construction projects (Israel, 2023; Sayi & Monko, 2022).

Third, the results suggest that there is a positive and significant relationship between competition and VfM achievement. This result shed light on the critical role of competition in enhancing VfM achievement, hence supporting existing literature (Panga, 2021; Sama, 2022; Israel, 2023) and the arguments behind the governance theory (Bevir, 2011; Glas et al., 2018). The significance of competition in the procurement bidding process, particularly in public construction projects has become paramount. Section 64 (1) of the Tanzanian PPA (CAP. 410 R.E. 2016) and the World Bank's procurement guidelines emphasise that competitive tendering should be the default method of procurement for public-funded projects. In line with the findings of this study and the propositions of governance theory, previous studies suggest that competition fosters transparency, accountability and fairness—important drivers of achieving VfM (Harnovinsah et al., 2020; Nyanyofio et al., 2022). Besides that, competitive bidding enables the selection of qualified contractors and consultants who have the capability to execute construction projects within the estimated time, cost and quality standards, hence supporting VfM achievement (Mrope et al., 2017; Asuquo et al., 2021).

The prominent finding for the last hypothesis is that integrity is a positive and significant predictor of VfM. This finding aligns with the study conducted by Obieje (2019), as well as the assumptions of governance theory (UNDP, 2007; Glas et al., 2018; Bevir, 2011). In line with the assumptions of governance theory (IMF, 2022), the study findings suggest that PEs can attain VfM in construction projects by upholding integrity-related practices. Integrity encompasses various aspects such as maintaining consistent bid evaluation criteria, following proper procedures for contractor selection and employment and ensuring compliance with contractual terms and conditions. These aspects are integral to achieving VfM in public construction projects (Changalima et al., 2022). By adhering to contractual terms and conditions, PEs can avoid fines and penalties. Moreover, when bidding procedures, evaluation criteria and specifications are streamlined and remain unaltered, PEs are better positioned to select competent and qualified contractors and consultants who are committed to executing construction projects within the agreed time, budget and quality standards (Israel, 2023; Weerasekara, Disaratna, Withanage, & Perera, 2021; Siwandeti et al., 2023), hence nurturing VfM achievement.

6. Conclusion, implications and future research

6.1 Conclusion

This study focusses on examining the strategic role of PGG in bolstering VfM achievement in public construction projects within the context of Tanzania. Four constructs (principles) of PGG, namely transparency, accountability, competition and integrity were adopted and analysed to assess their impact on VfM. The findings of the study indicate that the underlying principles of PGG play a significant and crucial role in enhancing VfM in public construction projects. Specifically, transparency, accountability, competition and integrity were positively and significantly associated with VfM achievement (p < 0.01). Based on these findings, we conclude that PGG serves as an important predictor of VfM in public construction projects. Therefore, to enhance VfM, public procurement officials and other stakeholders involved in the planning and execution of construction projects should diligently adhere to the principles governing public procurement procedures.

6.2 Theoretical implications

The findings of this study contribute to the advancement of governance theory by underscoring the significance of adhering to the principles of PGG for improved project outcomes and the achievement of VfM in public construction projects. It extends understanding from previous studies on how good governance can reinforce VfM in the public construction project landscape (Glas et al., 2018; Bevir, 2011; Talebi & Rezania, 2020). The findings of this study demonstrate that PGG and their respective principles can help PEs eliminate flaws and procurement malpractices that undermine cost-effectiveness, efficiency and effectiveness in public construction projects. This aligns with the assumptions of governance theory, emphasising the importance of nurturing transparency, responsiveness, accountability and integrity as crucial pillars for enhancing prosperity in public service delivery (Williams & Young, 1994; IMF, 2022; UNDP, 2007). Drawing on governance theory, the study suggests that PEs can achieve VfM in public construction projects by diligently placing strong emphasis on ethical standards, observing and complying with procurement regulations and laws, which are the core principles of governance theory.

By exploring the relationships between the study variables, this study contributes to the existing literature on the role of PGG in VfM achievement within public construction projects, an area that has received limited attention, particularly in the context of Tanzania. As mentioned earlier, present scholarly investigations focus on challenges and deficiencies hindering the achievement of VfM (Pastory, 2019; Matto, 2023; Israel, 2022), the drivers of cost and time overruns (Kavishe et al., 2018; Manege & Kennedy, 2020; Mchopa, 2015), as well as the perceived benefits of regulatory compliance in the public bidding process (Changalima et al., 2022; Sama, 2022; Panga, 2021). The current study enhances scholars' understanding of the theoretical model of good governance and VfM achievement in public construction projects from the perspective of PGG.

6.3 Managerial implications

Measures should be taken to ensure strict compliance with PGG throughout the entirety of public construction projects. Amongst others, the study recommends the implementation of regular training and capacity-building programs to enhance the knowledge and capabilities of construction project stakeholders, specifically in relation to procurement best practices for VfM achievement. Moreover, it is crucial to establish streamlined internal and external control mechanisms such as internal audit and oversight committees, with a mandatory role in enforcing and monitoring compliance with PGG. These measures will foster a sense of competition, transparency, accountability and integrity amongst procurement officials during the planning and execution phases of construction projects. Additionally, both public PEs and oversight authorities should develop standardised indicators of VfM in public construction projects. By utilising such indicators, PEs will be able to assess and identify areas of weakness that impede VfM achievement, leading to policy reforms and improvements.

6.4 Limitations and suggestions for future studies

Although this study achieved its overall objectives, it highlights a few limitations. First, the study was constrained by its cross-sectional research design and quantitative approach. The use of a quantitative research approach restricted the exploration and explanation of procurement practitioners' opinions on the study variables. Similarly, the cross-sectional design limited our ability to determine whether the collected opinions remain consistent or change over time. Furthermore, the study focussed exclusively on the opinions of public procurement practitioners, neglecting other important stakeholders such as suppliers, contractors, sub-contractors and consultants. Consequently, the analysis lacked a comprehensive perspective from a wide range of procurement and construction project practitioners. Considering these limitations, future studies should prioritise the use of longitudinal case studies to examine the consistency of PGG in estimating VfM over time. Additionally, it would be valuable to investigate the role of PGG in VfM achievement from the perspectives of service providers (suppliers, contractors, sub-contractors and consultants), thus complementing the perspectives of public procurement officials examined in this study. Finally, the study suggests that future research employs mixed methods to supplement the findings of the current study. By addressing the limitations of this study and pursuing these recommended avenues of research, scholars can deepen their understanding of the complex relationship between PGG and VfM achievement in public construction projects.

Figures

The conceptual framework

Figure 1

The conceptual framework

Measurement model

Figure 2

Measurement model

Structural model

Figure 3

Structural model

Demographic profile of respondents

VariableCategoryCount (n = 203)Percent
GenderMale13365.52
Female7034.48
Age groups21–30 years3416.75
31–40 years6431.53
41–50 years5828.57
51–60 years4723.15
Job positionHeads of procurement unit2311.33
Project managers2210.84
Heads of user departments2110.34
Project consultants2411.82
Accounting officers2311.33
Chairmen of the tender boards2411.82
Auditors4723.15
Heads of finance unit199.36
Level of educationDiploma3416.75
First Degree9144.83
Postgraduate7838.42
Working experience≥6 months ≤1 year146.90
>1 ≤ 5 years3115.27
>5 ≤ 10 years7134.98
>10 ≤ 15 years4522.17
>15 ≤ 20 years2411.82
>20 years188.87

Source(s): Table by authors

Measurements, factor loadings, reliability and validity

Constructs/ItemsλαCRAVE
Transparency (TRSP) 0.7810.8930.627
Trans1: PEs exclusively use e-procurement in procurement activities0.718
Trans2: Annual procurement plans are openly available to all bidders on time0.884
Trans3: Contractors are given equal chances to participate in bidding processes0.790
Trans4. PEs made tender notices publicly available to all bidders0.806
Trans5: PE carries public bid opening immediately after submission deadlines0.751
Accountability (ACC) 0.7060.7780.540
Acc1: Public officials comply with procurement laws and regulations0.462*
Acc2: PEs have streamlined mechanisms for logging rewards and punishments0.713
Acc3: Public officials accept liability to sanctions dues to unethical practices0.797
Acc4: PEs have streamlined procedures for reporting procurement malpractices0.691
Competition (COMP) 0.8840.8690.625
Comp1: PEs use competitive tendering as the default method of procurement0.706
Comp2: Bidders exclusively participate in a pre-qualification process0.838
Comp3: PEs exclusively carry out post-qualification processes0.876
Comp4: PEs avoid dividing contracts to circumvent thresholds for open tenders0.729
Integrity of contract (INTEG) 0.7410.9160.733
Integ1: PEs effect payment to bidders within a specified and agreed timeframe0.839
Inget2: Bidders receive interest on late payment0.919
Inget3: Evaluation criteria are kept unchanged after bids opening0.868
Integ4: PEs prohibit employing contractors who are improperly selected0.793
Integ5: PE properly aside funds before starting procurement processes0.409*
Value for money (VfM) 0.8350.9160.785
VfM1: PEs have achieved cost-effectiveness0.844
VfM2: PEs have achieved efficiency in construction projects0.903
VfM3: PEs have achieved acceptable quality in construction projects0.910

Source(s): Table by authors

Fornell–Larcker criterion measures of discriminant validity

CRAVEMSVASVCOMPTRANSACCINTEGVfM
COMP0.8690.6250.3410.1430.790
TRANS0.8930.6270.2530.1660.2960.792
ACC0.7780.5400.1770.0900.1060.4210.735
INTEG0.9160.7330.3410.1820.5840.3800.2740.856
VfM0.9160.7850.2530.1620.3660.5030.3090.4070.886

Note(s): Italicised values denote √AVE > correlation between constructs

Source(s): Table by authors

Hypothesised relationships between study variables

Regressed variablesStandardised
Estimate
Unstandardised
Estimate
S.E.C.R.P
VfM<---COMP0.1620.2300.0872.659***
VfM<---ACC0.1200.1250.0681.841***
VfM<---INTEG0.1990.2450.0753.283***
VfM<---TRANS0.3900.3990.0666.053***

Note(s): ***p < 0.001

Source(s): Table by authors

References

AfDB (2012). Rules and Procedures for Procurement of Goods and works. Tunis, Tunisia: Procurement and Fiduciary Services Department.

Anderson, R., Kovacic, W., & Müller, A. (2011). Ensuring integrity and competition in public procurement markets: A dual challenge for good governance. Cambridge: Cambridge University Press.

Asuquo, C., Lashinde, A., & Adu, E. (2021). Governance quality and public sector procurement of infrastructure projects in developing countries: Evidence from Nigeria. Journal of Public Procurement, 21(3), 285299. doi: 10.1108/jopp-10-2019-0067.

Bajjou, M. S. & Chafi, A. (2020). Empirical study of schedule delay in Moroccan construction projects. International Journal of Construction Management, 20(7), 783800.

Bauhr, M., Czibik, A., Licht, J., & Fazekas, M. (2020). Lights on the shadows of public procurement: Transparency as an antidote to corruption. Governance, 33(3), 495523. doi: 10.1111/gove.12432.

Bevir, M. (2011). Governance as theory, practice, and dilemma. Berkeley: The SAGE Handbook of Governance. London: Sage Publications.

Bosio, E., Djankov, S., Glaeser, E., & Shleifer, A. (2022). Public procurement in law and practice. American Economic Review, 112(4), 10911117. doi: 10.1257/aer.20200738.

Botlhale, E. (2017). Infusing value for money (VfM) into the public procurement system in Botswana. Journal of Public Procurement, 17(3), 281341. doi: 10.1108/jopp-17-03-2017-b001.

Brito, R. P., & Miguel, P. L. (2017). Power, governance, and value in collaboration: Differences between buyer and supplier perspectives. Journal of Supply Chain Management, 53(2), 6187. doi: 10.1111/jscm.12134.

Changalima, I. A., Ismail, I. J., & Mwaiseje, S. S. (2022). Obtaining the best value for money through procurement planning: Can procurement regulatory compliance intervene?. Journal of Money and Business, 2(2), 133148. doi: 10.1108/jmb-11-2021-0056.

Dominowski, R. L. (1980). Research methods. Englewood Cliff: Prentice-Hall.

Fan, Y., Chen, J., Shirkey, G., John, R., Wu, S. R., Park, H., & Shao, C. (2016). Applications of structural equation modelling (SEM) in ecological studies: An updated review. Ecological Processes, 5(1), 112.

Glas, A. H., Gaus, J., & Ebig, M. (2018). Effects of governance structures on sustainability- oriented supplier behaviour: Analysis of national action plans and their effects in public procurement. International Journal of Business Environment, 10(1), 7594. doi: 10.1504/ijbe.2018.093325.

Gomes, C. F., Small, M. H., & Yasin, M. M. (2019). Towards excellence in managing the public- sector project cycle: A TQM context. International Journal of Public Sector Management, 32(2), 207228. doi: 10.1108/ijpsm-11-2017-0315.

Gransberg, D. D., Molenaar, K. R., Scott, S., & Smith, N. (2007). Implementing best-value in highway construction projects. Reston, Virginia: Alternative Project Delivery, Procurement, and Contracting Methods for Highways.

Hair, J. F., Ringle, C. M., & Sarstedt, M. (2013). Partial least squares structural equation modelling: Rigorous applications, better results and higher acceptance. Long Range Planning, 46(1), 112. doi: 10.1016/j.lrp.2013.01.001.

Harnovinsah, H., Al-Hakim, Y., Erlina, E., & Muda, I. (2020). Effect of accountability, transparency and supervision on budget performance. Utopía Y Praxis Latino Americana, 25(7), 130143.

Heald, D. (2018). Transparency‐generated trust: The problematic theorization of public audit Financial Accountability & Management. Financial Accountability & Management, 34(4), 317335. doi: 10.1111/faam.12175.

Henseler, J., Ringle, C. M., & Sarstedt, M. (2015). A new criterion for assessing discriminant validity in variance-based structural equation modelling. Journal of the Academy of Marketing Science, 43(1), 115135. doi: 10.1007/s11747-014-0403-8.

Heravi, G., & Mohammadian, M. (2021). Investigating cost overruns and delay in urban construction projects in Iran. International Journal of Construction Management, 21(9), 958968. doi: 10.1080/15623599.2019.1601394.

Hsueh, L., Bretschneider, S., Stritch, J. M., & Darnall, N. (2020). Implementation of sustainable public procurement in local governments: A measurement approach. International Journal of Public Sector Management, 33(6/7), 697712. doi: 10.1108/ijpsm-09-2019-0233.

Ibrahim, M., Bawole, J. N., Obuobisa-Darko, T., Abubakar, A. B., & Kumasey, A. S. (2017). The legal regime and the compliance façade in public procurement in Ghana. International Journal of Public Sector Management, 30(4), 370390. doi: 10.1108/ijpsm-09-2016-0156.

Idrees, S., & Shafiq, M. T. (2021). Factors for time and cost overrun in public projects. Journal of Engineering, Project, and Production Management, 11(3), 243254.

IMF (2022). Good governance in sub-saharan Africa: Opportunities and lessons. Washington, D.C: International Monetary Fund.

Israel, G. D. (1992). Sampling the evidence of extension programme: Programme evaluation and organisational development. International Statistical Review, 47(2), 99109.

Israel, B. (2022). The impact of clients’ procurement challenges on the substance goals of roads construction projects in Songwe, Tanzania. International Journal of Construction Management, 23(12), 21442150. doi: 10.1080/15623599.2022.2045861.

Israel, B. (2023). A study of stakeholders' procurement deficiencies, delays and cost overruns in Tanzania's construction projects. International Journal of Procurement Management, 18(4), 489504. doi: 10.1504/ijpm.2023.134629.

Israel, B., Mchopa, A. D., Mwaiseje, S., & Mashene, A. (2019). Ethical procurement practices and performance of public procuring entities in Tanzania: Empirical evidences from moshi district council. Journal of Co-operative and Business Studies, 4(2), 3947.

Johnson, R. M., & Babu, R. I. (2020). Time and cost overruns in the UAE construction industry: A critical analysis. International Journal of Construction Management, 20(5), 402411. doi: 10.1080/15623599.2018.1484864.

Kafimbou, B. (2019). The conflict between the pursuit of integrity and performance in public procurement. Theoretical Economics Letters, 9(1), 12841298. doi: 10.4236/tel.2019.95083.

Kavishe, N., Jefferson, I., & Chileshe, N. (2018). An analysis of the delivery challenges influencing public-private partnership in housing projects: The case of Tanzania. Engineering, Construction and Architectural Management, 25(2), 202240. doi: 10.1108/ecam-12-2016-0261.

Kwofie, T. E., Ellis, F. Y. A., & Opoku, D. (2021). Significant governance factors in PPP infrastructure delivery performance in Ghana. Journal of Public Procurement, 21(2), 97118. doi: 10.1108/jopp-07-2019-0039.

MacKinnon, D. P., Lockwood, C. M., Hoffman, J. M., West, S. G., & Sheets, V. (2002). A comparison of methods to test mediation and other intervening variable effects. Psychological Methods, 7, 83103.

Mahuwi, L., & Israel, B. (2023). A review on participation of SMEs in public procurement: Opportunities, challenges, and policy implications. New Applied Studies in Management, Economics and Accounting, 6(4), 1833.

Manege, S. L., & Kennedy, C. J. (2020). Investigating whole life costing awareness in Tanzania building construction industry. International Journal of Construction Management, 22(15), 29142921. doi: 10.1080/15623599.2020.1832181.

Marinelli, M., & Antoniou, F. (2020). Improving public works’ value for money: A new procurement strategy. International Journal of Managing Projects in Business, 13(1), 85102. doi: 10.1108/ijmpb-04-2018-0084.

Matto, M. C. (2023). Identifying the latent shortcomings of force account projects in Tanzania: The case of construction projects in the education sector. Engineering, Construction and Architectural Management, 30(2), 787804. doi: 10.1108/ecam-06-2021-0525.

Matto, M. C., Ame, A. M., & Nsimbila, P. M. (2021). Influence of contract management on value for money procurement in Tanzania. International Journal of Procurement Management, 14(6), 724741. doi: 10.1504/ijpm.2021.117889.

McArdle, G., & Gunning, J. G. (2018). Enhancing value for money in public procurement of Northern Ireland construction projects. Management, Procurement and Law, 171(5), 207219. doi: 10.1680/jmapl.17.00023.

Mchopa, A. (2015). Integrating contract management practices into the achievement of value for money in Tanzania public procurement: Evidence from selected procuring entities in Moshi municipality. Journal of Public Procurement, 15(2), 129149. doi: 10.1108/jopp-15-02-2015-b001.

Mrope, N. P., Namusonge, G. S., & Iravo, M. A. (2017). Does compliance with rules ensure better performance? An assessment of the effect of compliance with procurement legal and regulatory framework on performance of public procurement in Tanzania. European Journal of Logistics, Purchasing and Supply Chain Management, 5(1), 4050.

Nyanyofio, J. G. T., Domfeh, K. A., Buabeng, T., Maloreh-Nyamekye, T., & Appiah-Agyekum, N. N. (2022). Governance and effectiveness of public–private partnership in Ghana's rural- water sector. International Journal of Public Sector Management, 35(7), 709732. doi: 10.1108/ijpsm-05-2021-0129.

Obieje, I. (2019). Improving the achievement of value for money in construction procurement under the Nigerian Public Procurement ACT (2007). UK: School of the Built Environment: University of Salford.

Oke, A. E., Aigbavboa, C. O., & Tong, B. A. (2018). Evaluation of procurement systems of public sector funded projects. In Proceedings of the 21st International Symposium on Advancement of Construction Management and Real Estate, Singapore. Springer.

Olatunji, S., Olawumi, T.O., & Awodele, O.A. (2017). Achieving value for money in construction projects. Civil and Environmental Research, 9(2), 5464.

Panga, F. P. (2021). Competitiveness in procurement cycle and value for money in local government projects in Tanzania: The quest for good governance. Journal of Co-operative and Business Studies, 6(2), 150161.

Pastory, P. (2019). Inter-governmental relations and procurement non-compliance in African local government systems: Insights from Tanzania. Journal of Public Procurement, 19(4), 277294. doi: 10.1108/jopp-01-2019-0001.

Sama, H. K. (2022). Transparency in competitive tendering: The dominancy of bounded rationality. Cogent Business and Management, 9(1), 117. doi: 10.1080/23311975.2022.2147048.

Saunders, M., Lewis, P., & Thornhill, A. (2019). Research methods for business students (8th ed.). Harlow: Pearson Education.

Sayi, M. D., & Monko, R. J. (2022). Hindrants to value for money achievement in force account projects. International Journal of Construction Engineering and Management, 11(1), 17.

Shakya, R. K. (2015). Good governance in public procurement: An evaluation of the role of an E-procurement system. Minneapolis, USA: Capella University.

Siwandeti, M., Mahuwi, L., & Israel, B. (2023). How public procurement can help societies achieve SDGs: A conceptual model. Management of Sustainable Development Journal, 15(1), 3646. doi: 10.54989/msd-2023-0006.

Staples, W. J., & Dalrymple, J. F. (2012). Value for money in public sector construction procurement. In Proceedings of the 26th Annual Australian and New Zealand Academy of Management Conference (ANZAM 2012), Perth, Western Australia, Australia.

Stoker, G. (2006). Public value management: A new narrative for networked governance?. American Review of Public Administration, 36(1), 4157. doi: 10.1177/0275074005282583.

Talebi, A., & Rezania, D. (2020). Governance of projects in public procurement of innovation a multi-level perspective. Journal of Public Procurement, 20(2), 187206. doi: 10.1108/jopp-01-2019-0005.

UND (2007). Governance principles, institutional capacity and quality. New York: UNDP.

URT (2011). Public procurement act (As amended in 2016). Tanzania: Public Procurement Regulatory Authority: Dar Es Salaam.

URT (2013). The public procurement regulations (As amended in 2016). Tanzania: Public Procurement Regulatory Authority: Dar Es Salaam.

URT (2021). The annual general report of the controller and Auditor general on the audit of development projects for the financial year ended 30th, June 2021. Tanzania: National Audit Office: Dar Es Salaam.

Weerasekara, D. T., Disaratna, V., Withanage, K. T., & Perera, B. A. K. S. (2021). Procurement management in the foreign-funded construction projects implemented in Sri Lanka. International Journal of Construction Management, 21(6), 113. doi: 10.1080/15623599.2021.1956674.

Williams, D., & Young, T. (1994). Governance, the World Bank and liberal theory. Political Studies, 42(1), 87100. doi: 10.1111/j.1467-9248.1994.tb01675.x.

Wolf, E. J., Harrington, K. M., Clark, S. L., & Miller, M. W. (2013). Sample size requirements for structural equation models an evaluation of power, bias, and solution propriety. Educational and Psychological Measurement, 73(6), 913934.

World Bank (2014). Procurement guidelines for goods, works, and non- consulting services under IBRD loans and IDA credits and grants by World Bank borrowers. Washington, DC: World Bank.

World Bank (2020). Procurement report in investment project financing goods, works, non- consulting and consulting services. Washington, DC: World Bank.

Further reading

Davey, J., & Gatenby, G. (2016). The government procurement review (5th Ed.). London: Law Business Research.

European Commission (2014). Report from the commission to the council and the European parliament - EU Anti-Corruption Report. Brussels, Belgium: European Commission.

Hooper, D., Coughlan, J., & Mullen, M. R. (2008). Structural equation modelling: Guidelines for determining model fit. Electronic Journal of Business Research Methods, 6(1), 5360.

Obura, C. (2019). Role of integrity in enhancing effective procurement practice in Kenya Bureau of Standards. European Journal of Business and Strategic Management, 4(2), 7786.