The development of a lean six sigma and BIM framework for enhancing off-site manufacturing

Olivia McDermott (College of Science and Engineering, University of Galway, Galway, Ireland)
Kevin ODwyer (Department of Engineering, University of Limerick, Limerick, Ireland)
John Noonan (Department of Computer Science and Information Systems, University of Limerick, Limerick, Ireland)
Anna Trubetskaya (Department of Engineering, University of Limerick, Limerick, Ireland and Department of Biosciences, Nord University, Steinkjer, Norway)
Angelo Rosa (Department of Management Studies, Università LUM Jean Monnet, Casamassima, Italy)

International Journal of Lean Six Sigma

ISSN: 2040-4166

Article publication date: 12 May 2023

80438

Abstract

Purpose

This study aims to improve a construction company's overall project delivery by utilising lean six sigma (LSS) methods combined with building information modelling (BIM) to design, modularise and manufacture various building elements in a controlled factory environment off-site.

Design/methodology/approach

A case study in a construction company utilised lean six sigma (LSS) methodology and BIM to identify non-value add waste in the construction process and improve sustainability.

Findings

An Irish-based construction company manufacturing modular pipe racks for the pharmaceutical industry utilised LSS to optimise and standardise their off-site manufacturing (OSM) partners process and leverage BIM to design skids which could be manufactured offsite and transported easily with minimal on-site installation and rework required. Productivity was improved, waste was reduced, less energy was consumed, defects were reduced and the project schedule for completion was reduced.

Research limitations/implications

The case study was carried out on one construction company and one construction product type. Further case studies would ensure more generalisability. However, the implementation was tested on a modular construction company, and the methods used indicate that the generic framework could be applied and customized to any offsite company.

Originality/value

This is one of the few studies on implementing offsite manufacturing (OSM) utilising LSS and BIM in an Irish construction company. The detailed quantitative benefits and cost savings calculations presented as well as the use of the LSM methods and BIM in designing an OSM process can be leveraged by other construction organisations to understand the benefits of OSM. This study can help demonstrate how LSS and BIM can aid the construction industry to be more environmentally friendly.

Keywords

Citation

McDermott, O., ODwyer, K., Noonan, J., Trubetskaya, A. and Rosa, A. (2024), "The development of a lean six sigma and BIM framework for enhancing off-site manufacturing", International Journal of Lean Six Sigma, Vol. 15 No. 8, pp. 50-69. https://doi.org/10.1108/IJLSS-02-2023-0020

Publisher

:

Emerald Publishing Limited

Copyright © 2023, Olivia McDermott, Kevin ODwyer, John Noonan, Anna Trubetskaya and Angelo Rosa.

License

Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial & non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode


1. Introduction

The construction industry is well known for being fundamentally labour oriented, having poor labour productivity, delayed project completion, not adhering to regulatory requirements, low sustainability, inefficient processes and exceeding planned budgeted costs (Bertram et al., 2019). In terms of productivity, it has lagged behind other industries, such as manufacturing, for years. The on-site construction method is costly, not environmentally friendly, highly inefficient and extremely risky, particularly in confined areas where several accidents, near-misses and disasters are common (Ginigaddara et al., 2022). The Global Status Report for Buildings and Construction confirmed that in 2020 alone, the construction industry was responsible for 28% of global energy-related carbon dioxide (CO2) emissions (United Nations Environment Programme, 2021). The risks with on-site construction can be higher because of the unpredictable working conditions, leading to many unwanted consequences.

Additionally, there is the risk of materials and equipment getting damaged on-site due to inadequate storage space (Spillane et al., 2011). The high number of employees on-site can be highly unproductive, cause significant schedule delays, and lead to a high risk of accidents and injuries. In 2019 alone, 9,335 non-fatal injuries were reported to the Irish Health and Safety Authority, of which approximately 850 happened in the construction industry (Health and Safety Authority, 2020). Moreover, the construction industry was significantly impacted by the Covid-19 pandemic, challenging the construction industry to improve the safety and well-being of its workforce (Pamidimukkala and Kermanshachi, 2021). Production in the construction industry across Europe peaked sharply in June 2020, reaching 21.3% (Eurostat, 2021). Due to this sudden increase in productivity post-Covid-19, organisations have greater challenges and increased risks, with client demands to compensate for lost time on delayed projects.

Despite the construction industry's shortcomings, modern construction methods (MMC), such as off-site manufacturing (OSM), are significantly improving the efficiency of how projects are delivered. Research by Zhang et al. (2020) found that applying lean tools to the OSM process created great potential for design optimisation and a more efficient construction process. Lean has been increasingly utilised in the construction industry to improve the productivity and sustainability (Babalola et al., 2019). Several studies have highlighted how construction industry stakeholders are exploring new processes, techniques and practices they see as having the potential to move the industry towards being environmentally friendly, less wasteful and leaner in terms of their project delivery (Dallasega et al., 2018; Lu and Yuan, 2011; Stehn and Höök, 2008).

The case study construction organisation where this research occurred must enhance its construction capabilities to significantly improve its overall project efficiency and reduce the risk of negative impacts on the client or their business. Currently, the organisation has on-site construction and this process.

The main objective of this project was to improve the construction delivery process in OSM by deploying lean six sigma (LSS) and building information modelling (BIM) to reduce waste and improve green practices.

Following the introductory section, Section 2 provides a literature review, and Section 3 discusses the research design and methodology and provides the background of the study. Section 4 presents analyses of findings. Finally, Section 5 discusses the results, while Section 6 concludes with the practical lessons learned and future research opportunities.

2. Literature review

2.1 Lean in construction

Mahmood et al. (2014) describe a construction project as a one-time activity completed within a defined scope, schedule and budget. Construction projects are very capital-intensive and characterised by lengthy, complicated and interconnected processes of planning, design and execution (Rosenfeld, 2009). Consequently, the construction industry has challenges with including non-value-adding activities and processes in its value stream, resulting in inefficiencies, low productivity and sometimes poor quality (Olanrewaju and Abdul-Aziz, 2015). In many ways, inefficiency in the construction industry is budget overruns resulting from delays in meeting project delivery timelines and material wastage (Hussin et al., 2013). The construction industry has embraced Lean to be less wasteful and more sustainable in recent years (Hussin et al., 2013; Lu and Yuan, 2011). While Lean has been extensively embraced in manufacturing (Antony et al., 2018; Duggan et al., 2022; McDermott et al., 2022b; Nelson et al., 2022; Snee, 2010), healthcare (McDermott et al., 2022a) and higher education (Antony, 2014), it has started to emerge more in studies related to construction in the late to early 2000s (Babalola et al., 2019; Feng and Ballard, 2008; Howell and Ballard, 1998).

The work on lean construction started in the early 1990s and focused on two major areas in understanding the application and implementation of production principles in construction. These principles were about understanding construction as a production process and planning and managing the workflow within the construction process (Bertelsen, 2002; Howell and Ballard, 1998; Koskela et al., 2002). For example, “last planner” refers to the project team assigning work to specific performers and ensuring they have the materials, equipment and information to complete their assignments (Howell and Ballard, 1998).

Benefits of Lean in construction have been shown to achieve reduced construction times and costs, increased productivity, improved quality and increased customer value and satisfaction for customers; reduced consumption of resources, water and energy; reduction of emissions of particulates, noise and waste; improved health and safety at work and communication (Carvajal-Arango et al., 2019).

Research by Zhang et al. (2016) also found positive results when lean tools were applied for optimising work schedules, managing the allocation of materials and equipment, production just-in-time (JIT) and planning congestion-free work environments. However, lean tools are typically only introduced into the construction industry to improve project management, specifically to reduce the schedule duration and costs.

The construction industry has recently embraced the lean and green agenda (Garza-Reyes, 2015). Green building, for example, is one of the measures put forward to mitigate the significant impacts of the building stock on the environment, society and economy (Zuo and Zhao, 2014). The construction industry has embraced lean principles and green initiatives, realising the interlinkages between the two agendas (Ahuja et al., 2017). The industry recognises waste reduction as the common characteristic of both philosophies, with “waste” being defined differently (Carvajal-Arango et al., 2019). In the case of lean construction, the seven types of lean waste are discussed (Howell and Ballard, 1998). In contrast, in the case of sustainable construction, waste refers to material and energy wastes resulting from inefficient use of resources and excessive consumption of materials and energy, emissions, pollution and bad working conditions (Verrier et al., 2016). Carvajal-Arango et al. (2019), in a study on lean and sustainability in construction, found that of 56 lean practices, the majority led to positive effects on economic and environmental aspects.

2.2 Lean and sustainable construction

OSM and modularisation are MMC comprising designing, manufacturing and assembling various building elements off-site in a controlled factory environment before transporting them to the site (Goodier and Gibb, 2007). This OSM construction method enables a faster on-site build with a much higher finish grade than the stick build process. However, OSM has attracted limited attention from researchers and industry stakeholders, particularly in developing countries (Durdyev and Ismail, 2019; Sahin et al., 2018). OSM and modularisation are similar techniques, equating to assemblies and subassemblies manufactured in a controlled off-site environment (da Rocha and Kemmer, 2018). Peltokorpi et al. (2018) describe OSM and modularisation as playing major roles in the standardisation and industrialisation of construction processes, resulting in increased client value and more effective processes when utilising the workforce and their time. Sawhney et al. (2020) state that the construction industry is on the cusp of a badly needed transformation with the pervasive use of lean tools, smart technology and OSM.

One way to encourage the adoption of prefabrication and OSM techniques and modular construction is to improve efficiency by utilising lean, which makes the technology more attractive to construction companies (Goh and Goh, 2019). Lean has been widely applied to improve the productivity and efficiency of construction projects, while modelling and simulation enhance Lean benefits by allowing the design and benefits to be analysed quantitatively before implementation (Goh and Goh, 2019; Matthew, 2017). However, the main challenge of lean OSM construction is related to the continuous production flow at the off-site factory. At the construction site, the flow is turbulent and unpredictable, with issues such as changes in customer demand or site conditions delaying customer orders (Mostafa et al., 2014).

2.3 Lean and digital technologies in construction

Increasingly, studies demonstrate BIM as an enabler for Lean construction (Peiris et al., 2022). Studies have demonstrated the application of lean construction and advanced digital technologies, particularly BIM, to improve project quality, productivity and performance (Aziz and Zainon, 2022). Technologies such as BIM as an innovative digital technology, point cloud scanning and virtual/augmented reality (VR/AR) installation equipment have a major impact on how construction projects are delivered (Enshassi et al., 2018).

BIM enables the creation of information-rich and accurate simulation models. According to Eldeep et al. (2022), utilising BIM as a lean tool reduces owner-initiated changes and design errors/omissions by more than 80% due to BIM's ability to detect mistakes or omissions in the pre-construction stage. Utilising BIM helps create planning for Lean principles of pull, improving flow and adding value (Bhattacharya and Mathur, 2022).

Advanced technologies, particularly BIM, are also contributing to green building development (Zuo and Zhao, 2014). Many researchers have also asserted a strong synergy between BIM, lean and green by confirming the lean and green benefits achieved through BIM implementation on construction projects (Ahuja et al., 2014, 2017). BIM enables lower additional building costs, adoption of passive design strategies and re-use of materials to reduce the environmental impacts of construction activities, perform energy analysis and design for optimal energy consumption (Rahman et al., 2013).

2.4 Conclusion

Having reviewed the literature, it is evident that lean in construction has evolved in recent years and that the literature is related to the topic. Lean has been shown to have many benefits for construction, such as improving the quality of builds, reducing defects and rework, preventing material wastes, cost reduction and improving adherence to schedule. However, there are fewer practical applications in the literature related to lean in construction than in manufacturing. Construction differs from most manufacturing functions as it is a mixture of providing a service and a product. Project management methodology, budgeting and scheduling are integral to managing construction projects, and lean must be merged with project management methodology to deliver successful projects.

3. Methodology

3.1 Background to the case study organisation

A case study approach is most suitable for a study where work is scarce on the subject (Yin, 2011), as there is literature on maximising benefits from Lean and sustainable construction case studies (Babalola et al., 2019). Moreover, it further helps to better understand the context and setting to understand the phenomenon under study (Yin, 2016).

The chosen method for conducting this research was a case study utilising LSS within an Irish-based construction company. The company was manufacturing production equipment using “skids”. A skid is a common steel-framed platform-like structure over which heavy equipment is placed to facilitate easy movement and storage. It is constructed from I-beams, angles or channels and used as a shipping and support platform for various types of equipment. Typically, the company manufactures modular pipe racks for the pharmaceutical industry (Plate 1).

The off-site element of the construction was completing the welding on scaffolds. Skid systems are custom manufactured by fabricators as per the client's requirements. Once assembled, the equipment can be permanently mounted on the skid with all process controls in one spot (Trenchless, 2022). Once installed, the skid can be easily transported to the final site location, where the process can be quickly started.

3.2 DMAIC methodology

The project was achieved by adopting a LSS methodology of define, measure, analyse, improve and control (DMAIC) and by researching, applying and analysing various lean tools.

The research question will be explored through the use of the DMAIC method to:

  • Define the problem or research question via the use of supplier, inputs, processes, outputs, customer (SIPOC) and voice of the customer (VOC);

  • Quantitative financial, productivity, timeliness, qualitative quality and safety data in relation to on-site manufacturing costs and schedules will be collected through interaction with relevant stakeholders, creating a value stream map (VSM) and brainstorming with stakeholders;

  • Problems will be analysed using analyse tools such as the cause and effect and five whys to aid in finding a root cause;

  • Kaizen and a future VSM were utilised to identify and drive improvements to the root causes identified in the analysis phase; and

  • Control – actions implemented were monitored, and “after” data was collected in relation to productivity, quality, safety, waste and timeliness and compared with the “before” project measures.

DMAIC was the chosen methodology because it aligned with the organisation's existing strategy for problem-solving and continuous process improvement. Lean complements six sigma, as lean drives waste reduction and six sigma drives variation reduction (George, 2002). A DMAIC matrix was developed (Table 1), identifying the various tools and techniques utilised throughout the DMAIC project lifecycle.

An important element of research is benchmarking and observation. At this point in the research, OSM facilities were visited to observe the OSM process in operation.

4. Results

The study's results are outlined below with examples of how the DMAIC process was followed, and the following tools, as referenced in Table 1, are demonstrated. In addition, the following are presented: 1. SIPOC, 2. VOC, 3. current VSM, 4. wastage analysis, 5. cause and effect and 6. future VSM, including examples of JIT and improvements from Kaizen.

4.1 DMAIC process results

4.1.1 Defining the problem.

Firstly, a SIPOC diagram was drawn to understand the internal and external customer requirements (Figure 1).

A VOC analysis was subsequently utilised to capture the customer requirements as outlined in Table 2.

The construction company under study decided that based on the SIPOC and VOC analysis, there was an opportunity to utilise DMAIC to optimise the OSM process and eliminate on-site construction. The opportunity for OSM utilising skids was identified as having the potential for large savings but also for the benefits of deploying lean and green practices during the manufacturing process. As mentioned, a skid is a process scope within a frame that allows the processing unit to be easily transported (Lusardi, 2019). A skid is a system that comprises main equipment such as pumps, heat exchangers, filters and vessels. It is assembled with interconnecting pipework with inline items such as control valves, isolation valves and instruments to control and monitor the skid system. A production skid is a frame within which equipment is mounted and used for production purposes (Figure 2). Skid designs can vary, but the aim is to create a modular package easily slotted into an area. A process skid will incorporate components for production into the skid, such as a vessel, agitator, pumps and valves, heat exchangers and control panel for in situ adjustments (Flexachem, 2023).

After an extensive design process which involved the development of a BIM 3D model (Figure 3), piping and instrument drawings (P&IDs) and isometric drawings of the OSM design were issued to the client (a pharmaceutical organisation) by the construction organisation to approve the design for modular pipe racks. A piping and instrumentation diagram, or P&ID, shows a physical process flow's piping and related components (Lucidchart, 2022). These types of drawings are most commonly used in the engineering field. For example, BIM 3D and P&ID are used in conjunction with lean methodology in the construction industry to provide a visual of the process, aid sequencing and identify waste (Al-Saeed et al., 2020; Tauriainen et al., 2016; Tommelein, 1998).

4.1.2 Measure and analysis.

The main objective of the measure phase was to establish the current state VSM of the OSM production process and identify areas for the removal of waste and for improving efficiency. To achieve this, several “go to the Gemba” steps and observations of the process in operation were held. The output of these workshops was the development of the current-state VSM (Figure 4), which included the full value stream from client order to final delivery to the site.

The analysis phase consisted of analysing and understanding the inefficiencies and the root causes of the inefficiencies in the OSM process. Using the cause and effect analysis and five whys enabled the stakeholders to solve the problem (Figure 5 and Table 3).

The aforementioned tools and analysis of the current state of the VSM helped identify several areas (Table 4) that would benefit from implementing lean tools and techniques throughout the various process steps. Wastage or non-value add waste analysis was utilised to identify various Muda, Mura and Muri types. The lean eight wastes acronym of TIM WOODS was used to classify the wastes into Transport, Inventory, Motion, Waiting, Overprocessing, Overproduction, Defects or under-utilisation of employee Skillsets as applicable.

After the analysis, the future state map was drawn up in Figure 6. Following the completion of the future state map, a milestone implementation plan was developed, capturing the major milestones and how and when the future state VSM would be achieved. The future VSM was designed to reduce operator overtime (Muri), increase the production time and lower the hours worked at each step, create flow, eliminate Muda and make the process mistake-proof where possible. The improvements taken are highlighted in Table 4.

4.1.3 Improve.

In tangent with the future VSM and brainstorming of solutions, a Kaizen rapid improvement event (RIE) was held. The actions generated from the Kaizen are outlined briefly in Table 4 and expanded below.

The two-day Kaizen RIE commenced with a full 5S clean-up of the off-site facility. In addition, other potential improvements highlighted as part of the analyse phase and highlighted in the future VSM were implemented, such as 5S, Poke Yoke, Standard work and JIT. Furthermore, a just-in-time (JIT) delivery designed as part of the future VSM process aided the delivery of skids and super skids for final installation – delivered only as they were required on site. Thus, no delays were incurred, which are often caused when deliveries must be stored in a laydown or staging area before installation.

4.1.4 Control and savings.

The project's initial objective was to reduce waste in the construction process and aim to meet the VOC requirements of improved productivity, quality, timeliness and financial and safety measures.

The project met all of the aforementioned objectives, as outlined below.

Implementing the lean tools in the OSM process increased production time by 8 h whilst reducing the work hours required by 8 h, resulting in a 16-h per week production time-saving. The average employee cost calculated at €40ph over the 30 weeks meant a total saving of €19,220.00 was achieved (Table 5).

Thus, this enabled productivity, timeliness and financial benefits, providing benefits to the construction organisation and the client.

The contractor submitted progress reports weekly for review to ensure the targeted project milestones were achieved per the project schedule. This project also implemented a quality and lean reward scheme, whereby awards were presented regularly for process improvement suggestions, lean tools and excellent quality standard work. Recognition and reward are critical success factors for effective LSS implementation (McDermott et al., 2022b).

4.2 Comparison of off-site manufacturing savings with on-site construction

As is typical in the construction industry, this was a customised project. The significance of the project customisation is that it is impossible to compare the OSM process accurately with the traditional on-site stick build process (as no one project is ever the same).

To complete the analysis, the project costings were reviewed and compared with previously completed similar projects, and estimates were made of the cost savings. Table 6 shows a high-level overall costing estimation for the project. To calculate the savings, the following costs were collected: 1. The design cost of the OSM versus the on-site construction; and 2. The building cost of the OSM versus the on-site construction.

While the design cost for OSM was an additional €30,000, a saving of €320,000 was achieved by completing the work off-site. This resulted in an estimated project cost savings of €179,220.00 (OSM + lean and BIM framework).

Financial benefits are often viewed as the most powerful influence on building methods. However, the motivation for this project was also the recognition of the link between OSM and the increase in employee health and well-being, along with the environmental and economic impact. In Table 7, the environmental, social and economic statistics show a high-level estimation of the overall improvements.

Eight different measures were calculated related to traffic, energy used in manufacturing and on-site installation, amount of waste material, energy used, schedule length, cash flow, rework hours and on-time schedule.

The project aimed to reduce process and environmental waste and deliver the project on schedule and within budget without any adverse quality or safety issues. All key performance metrics were met and exceeded. There were no unanticipated or adverse results of the project.

4.3 Delivery of skids to on-site construction location

All elements within the skids were maximised to minimise follow-on work by on-site contractors, thus eliminating material wastage, non-value add work and rework time. OSM, utilising Lean and BIM, delivered a safe process and a completed project. All project specifications were met, and thus, there was a smooth transition through the commissioning and start-up of the new manufacturing plant. A working environment was created where integrated contractors could maximise productivity based on good safety practices, schedule compliance and quality management to meet mechanical completion. Ultimately, the project was also a financial success with the delivery of an affordable global solution for the construction process, and density challenges within the building were overcome by removing on-site work hours off-site, which saved high costs.

The main barriers or unanticipated problems encountered were the complexity of the design, the difficulties with transportation logistics and the required high level of engineering. The larger super skids and even some standard-sized skids required specific transportation considerations, which could have resulted in slight delivery delays and incurred additional costs, adding to the complexity. Detailed road surveys at the planning stage proved to be a key factor in ensuring effective project coordination and on-time delivery.

Even though the cost was considerably less for the OSM process, it required the onboarding of a company with an established manufacturing facility. The OSM process also required suppliers, contractors, designers and engineers who were experienced in and knowledgeable about the OSM process for construction. The lack of such experts in Ireland is a considerable constraint for implementing this process on a larger scale.

Both the research and the application of the research indicate that the sustainability of the construction industry is highly dependent on using the OSM process.

5. Discussion

The main research objective of this study was to improve the construction delivery process in OSM by deploying LSS and BIM methods to reduce waste and improve lean and green practices.

Firstly, the research demonstrates that for the construction industry to reach the productivity levels of other industries, they must consider the OSM process where possible during the building design process (Durdyev and Ismail, 2019). While there were increased design costs in developing the OSM project design for this project, the design efforts and plan delivered an end saving of 32% overall. Furthermore, the research also demonstrates that by utilising a lean framework with BIM for the OSM process in the design phase, the construction process can be significantly enhanced, wasteful activities can be removed and efficiency can be maximised. This finding is consistent with much of the literature on integrating lean, green and BIM in construction (Ahuja et al., 2014; Tauriainen et al., 2016). OSM reduced the personnel required for on-site construction and increased site productivity. BIM modelling aided skid and super skid module construction on the OSM site parallel to the on-site construction, reducing the overall project schedule duration. BIM also aided the designing and fabrication of key process elements to a consistent and repeatable level so that the skid modules could be delivered and assembled in the shortest time possible using a last planner system (Ahuja et al., 2014; Al-Saeed et al., 2020; Eldeep et al., 2022; Tauriainen et al., 2016).

All elements within the skids were maximised to minimise follow-on work by on-site contractors, thus eliminating material wastage, non-value add work and rework time. OSM, utilising lean and BIM, delivered a safe process and a project completed with zero safety incidents (Hu and Chong, 2021). All project specifications were met, and thus, there was a smooth transition through the commissioning and start-up of the new manufacturing plant. A working environment was created where integrated contractors could maximise productivity based on good safety practices, schedule compliance and quality management to meet mechanical completion. Ultimately, the project was also a financial success with the delivery of an affordable global solution for the construction process, and density challenges within the building were overcome by removing on-site work hours off-site, which saved significant costs (Tauriainen et al., 2016).

Furthermore, a just-in-time (JIT) delivery designed as part of the future VSM process aided the delivery of skids and super skids for final installation – delivered only as they were required on site. Thus, no delays were incurred, which are often caused when deliveries must be stored in a laydown or staging area before installation. A well-designed JIT system with OSM is integral to the success of on-site construction and reducing environmental waste (Hu and Chong, 2021).

5.1 Challenges to the off-site manufacturing process

With the OSM and modularisation process, some challenges required considerable coordination, collaboration and planning. This was similar to findings described by O’Connor et al. (2016), which found that the project planning process for OSM and modular construction differed by approximately 37% from the project planning of traditional construction methods. Many sectors, including the construction sector, are still adopting digital technologies and their integration with lean. This study demonstrated that there is a synergistic relationship between lean and digital technologies and aligns with literature related to their combined use (Antony et al., 2021, 2022; Tortorella and Fettermann, 2018).

6. Conclusion

This research demonstrates how OSM can be designed and improved by utilising LSS integrated with BIM modelling to design a project that increases productivity, quality and sustainability. The study met its objective to improve the construction delivery process in OSM by deploying LSS and BIM to reduce waste and improve green practices.

A limitation of this study is that it was only carried out on one organisation as a case study, but the results could be leveraged and generalised compared to on-site construction.

The implications of this study are both managerial and theoretical. The obtained results contribute to a body of knowledge on lean construction and provide practical knowledge for project professionals to adopt and implement lean construction.

From a managerial viewpoint, this study can be benchmarked by other construction organisations. The research introduces: 1. means for improving OSM processes specifically; and 2. measures for implementing digitalisation in off-site construction by positioning BIM as the key technology and lean principles to add value and reduce waste. Furthermore, industries can see evidence that the OSM process can be highly improved and yield significant gains by deploying a lean approach and implementing lean tools and techniques.

The theoretical implications of the study are that it serves as a case study for academics to demonstrate how LSS can be applied in a construction setting and thus demonstrates how LSS continues to have applicability across all sectors.

The main conclusions and recommendations are summarised as follows:

  • The appraisal of the literature and the research indicates that, furthermore, in addition to the numerous benefits inherent in the OSM process, there are also challenges that require strategic planning during the project's design stage.

  • OSM is a sustainable process for achieving social equality, economic prosperity and environmental quality.

  • To deliver operational excellence throughout the project lifecycle, construction companies must consider developing a lean or LSS framework and integrating it with digital technologies to enhance their OSM capabilities.

  • While traditional methods and approaches to construction will always be necessary, organisations must adopt new techniques to improve continuously. The implementation of lean methodologies in the OSM process has huge potential in relation to the reduction of waste, time and materials.

Future research opportunities exist to carry out more case studies in the organisation on how the LSS methods and BIM are deployed and developed for future projects, as there is much potential to maintain and enhance the benefits achieved. In addition, the researchers would also like to further research the deployment of the more developing digital technologies associated with LSS methods, such as BIM, 3D modelling, VR and AR, in the construction industry.

Figures

SIPOC diagram

Figure 1.

SIPOC diagram

A production skid

Figure 2.

A production skid

BIM 3D skid model shot

Figure 3.

BIM 3D skid model shot

Current state VSM

Figure 4.

Current state VSM

Cause and effect diagram

Figure 5.

Cause and effect diagram

Future state VSM

Figure 6.

Future state VSM

Modular pipe racks in skids

Plate 1.

Modular pipe racks in skids

DMAIC project steps

DMAIC Deliverables Tools and techniques Purpose
Define Establish objectives
Define the problem
Formulate a plan
Clarify the reasons
Stakeholder approval
Develop implementation and communication plan
Brainstorm Generate ideas
Share knowledge
Problem-solving
Strategize
Supplier, inputs, process, outputs, customer diagram (SIPOC) Establish boundaries
Identify inputs and outputs
Develop an understanding of the process
Voice of the customer (VOC) Identify key drivers of client satisfaction
Measure Assess the current state of design, OSM and project delivery Current state value stream map (VSM) Establish the current state
Analyse Analyse the current state to identify improvement areas and areas for eliminating waste Ishikawa/6M’s Focus on the team
Investigate root causes
Problem-solving
Analyse cause and effects
5 Whys Determine the root cause of any problems.
Find solutions, analyse and eliminate
Improve Implement lean tools and techniques Standard work Work should be standardised before it can be improved
Establish precise procedures
Establish effective methods
Poka Yoke Prevent errors
5S Sort, set, shine, standardise and sustain
Ensure that work areas are kept clean
Ensuring employee safety
Future state VSM Remove non-value add, eliminate waste, improve workflow and measure improvements
Kaizen rapid improvement event (RIE) Set aside other jobs to focus on working together to develop, test and implement the lean tools over 2 days
Just in time (JIT) Ensure the assembly is delivered only when required
Control Verify improvements
QC inspection/sign off.
Monthly quality audits
Data analysis Check progress
Verify improvements
VSM future state map Re-measure future state until desired objectives are achieved

Source: Authors’ own

VOC analysis

Voice of the customer matrix
Customer requirements (What are they saying?) Priority (What is the priority?) Customer requirement (What is the measurable target?)
Project delivered on time Timeliness On schedule
Project delivered correctly/right Quality Issue free installation
Project delivered on budget Financial Reduced cost
Project site installation (on schedule) Productivity No over runs on site
Project delivered with no safety issues Safety No safety incidents

Source: Authors’ own

Five whys example

Five whys
Why 1 Why 2 Why 3 Why 4 Why 5
Why? Because Why? Because Why? Because Why? Because Why? Because
Why is the cutting process taking so long? Because there is missing equipment Why is there missing equipment? Because equipment is missing and cannot be found Why is equipment missing and cannot be found? Because the storage and layout poor Why is the storage and layout poor? Because there are no designated area/storage areas or equipment for the area Why is there no designated storage/equipment? Because there is no organisation or 5S/housekeeping

Source: Authors’ own

Wastage analysis (analysis of process waste from current and future VSM)

Process steps Examples of waste Causes Corrective actions
Generated from the Kaizen
1. Cutting Muri: The operator in the cutting step was working a 10-h shift to meet the demand of the other process steps while achieving just 4 h of production time
Overprocessing: No jig in place operator measuring material for every cut
Lack of material organisation and storage
Equipment not set up for standardised work
Standard work and an extra operator were introduced to improve the flow
5S system set up with equipment
2. Grinding Waiting: Significant production time was lost due to waiting for material from the cutting step A bottleneck in cutting step Standard work was implemented, and an extra operator in cutting reduced the bottleneck
3. Tacking Waiting/motion/transport:
Lost production time due to lack of tools -missing jigs and clamps
Defects: Wrong tools used
Lack of correct equipment
Operator error
5S system set up with new equipment.
Poke Yoke introduced
4. Welding Overburdened: welder
10-h shifts
High defects – scrap levels
Bottleneck
More resources required
Standard work was implemented, and a new welder was added to improve the flow
Poke Yoke introduced
5. Cleaning Waiting: on welding Bottleneck from the previous station Eliminated with the new welder
6. QC check Overprocessing – manual steps printing, writing, scanning Not automated A new process with standard work and an Automated scanner introduced
7. Wrapping Waiting on welding Bottleneck Eliminated with a new welder. Merged with QC check
8. Shipping Transport/waiting/inventory of skids Outgoing inventory build-up/no space/delays in getting on site A just in time (JIT) daily delivery of skids was implemented (just as required on site)

Source: Authors’ own

Savings

Current state VSM vs future state VSM
VSM Hours worked Production hours Saving
Current 64 33
Future 56 41
−8 h worked +8 production time 16 h pw
@ €40ph = €320 saving @ €40ph = €320 saving €640pw
Project duration 30 weeks @ €640pw saving Total saved €19,220.00

Source: Authors’ own

Savings from OSM versus on-site project

Costs OSM On-site % Savings
(=/−)
Design cost €90,000 €60,000 −50% (−30,000)
Build cost €250,000 €440,000 +43% (+190,000)
Total €340,000 €500,000 +40% (+160, 000)
Total saving with OSM €320,000 = 32% savings overall

Source: Authors’ own

Environment, social and economic statistics

Category OSM % improvement
Less traffic ≥50
Less energy-used-on-site ≥75
Less waste ≥60
Less energy-in-use ≥15
Health and safety ≥85
Shorter schedule ≥50
Increased cash flow Substantial
Fewer punches/snags
(less-re-work)
≥90

Source: Authors’ own

References

Ahuja, R., Sawhney, A. and Arif, M. (2014), “BIM-based conceptual framework for lean and green integration”, Citeseer, pp. 123-132.

Ahuja, R., Sawhney, A. and Arif, M. (2017), “Driving lean and green project outcomes using BIM: a qualitative comparative analysis”, International Journal of Sustainable Built Environment, Vol. 6 No. 1, pp. 69-80. available at: www.sciencedirect.com/science/article/pii/S2212609016300991

Al-Saeed, Y., Edwards, D. and Scaysbrook, S. (2020), “Automating construction manufacturing procedures using BIM digital objects (BDOs) case study of knowledge transfer partnership project in UK”, Construction Innovation, Vol. 20 No. 3, pp. 345-377. WOS:000512156700001.

Antony, J. (2014), “Readiness factors for the lean six sigma journey in the higher education sector”, International Journal of Productivity and Performance Management, Vol. 63 No. 2, pp. 257-264, doi: 10.1108/IJPPM-04-2013-0077.

Antony, J., Gupta, S., Sunder, V.M. and Gijo, E.V. (2018), “Ten commandments of lean six sigma: a practitioners’ perspective”, International Journal of Productivity and Performance Management, Vol. 67 No. 6, pp. 1033-1044, doi: 10.1108/IJPPM-07-2017-0170.

Antony, J., McDermott, O., Powell, D. and Sony, M. (2021), “Mapping the terrain for lean six sigma 4.0. learning in the digital era”, 1st ed. Learning in the Digital Era, IFIP Advances in Information and Communication Technology 610, Springer, Cham, pp. 193-204, doi: 10.1007/978-3-030-92934-3_20.

Antony, J., McDermott, O., Powell, D. and Sony, M. (2022), “The evolution and future of lean six sigma 4.0”, The TQM Journal, Vol. 1, doi: 10.1108/TQM-04-2022-0135.

Aziz, N.M. and Zainon, N. (2022), “Driving factors for lean-BIM implementation in Malaysia’s construction industry: qualitative interview-based study”, Smart and Sustainable Built Environment, Vol. 1, doi: 10.1108/SASBE-01-2022-0019.

Babalola, O., Ibem, E.O. and Ezema, I.C. (2019), “Implementation of lean practices in the construction industry: a systematic review”, Building and Environment, Vol. 148 No. 15, pp. 34-43. Available at: www.sciencedirect.com/science/article/pii/S0360132318306760

Bertelsen, S. (2002), “Bridging the gap – towards a comprehensive understanding of lean construction”, IGLC-10, Gramado.

Bertram, N., Fuchs, S., Mischke, J., Palter, R., Strube, G. and Woetzel, J. (2019), “Modular construction: from projects to products | McKinsey”, available at: www.mckinsey.com/capabilities/operations/our-insights/modular-construction-from-projects-to-products

Bhattacharya, S. and Mathur, A. (2022), “Synergising lean objectives through BIM to enhance productivity and performance”, International Journal of Productivity and Performance Management, Vol. 1, doi: 10.1108/IJPPM-04-2021-0199.

Carvajal-Arango, D., Bahamón-Jaramillo, S., Aristizábal-Monsalve, P., Vásquez-Hernández, A. and Botero, L.F.B. (2019), “Relationships between lean and sustainable construction: positive impacts of lean practices over sustainability during construction phase”, Journal of Cleaner Production, Vol. 234 No. 10, pp. 1322-1337. Available at: www.sciencedirect.com/science/article/pii/S0959652619317500

Dallasega, P., Rauch, E. and Frosolini, M. (2018), “A lean approach for real-time planning and monitoring in engineer-to-order construction projects”, Buildings, Vol. 8 No. 3, p. 38.

da Rocha, C.G. and Kemmer, S. (2018), “Integrating product and process design in construction”, Construction Management and Economics, Vol. 36 No. 9, pp. 535-543, doi: 10.1080/01446193.2018.1464198.

Duggan, J., Cormican, K. and McDermott, O. (2022), “Lean implementation: analysis of individual-level factors in a biopharmaceutical organisation”, International Journal of Lean Six Sigma, Vol. 1, doi: 10.1108/IJLSS-10-2021-0184.

Durdyev, S. and Ismail, S. (2019), “Off-site manufacturing in the construction industry for productivity improvement”, Engineering Management Journal, Vol. 31 No. 1, pp. 35-46, doi: 10.1080/10429247.2018.1522566.

Eldeep, A., Farag, M. and Abd El-Hafez, L.M. (2022), “Using BIM as a lean management tool in construction processes – a case study”, Ain Shams Engineering Journal, Vol. 13 No. 2, p. 101556. Available at: www.sciencedirect.com/science/article/pii/S2090447921003075

Enshassi, A., Hamra, L.A.A. and Alkilani, S. (2018), “Studying the benefits of building information modeling (BIM) in architecture, engineering and construction (AEC) industry in the Gaza Strip”.

Eurostat (2021), “Eurostat”, Eu.europa.eu. Europa, available at: https://ec.europa.eu/eurostat/data/database

Feng, P.P. and Ballard, G. (2008), “Standard work from a lean theory perspective”, The Annual Conference of the International Group for Lean Construction: 10.

Flexachem (2023), “Production skids Inoxpa Flexachem”, available at: www.flexachem.com/production-skids/ (accessed 20 January).

Garza-Reyes, J.A. (2015), “Lean and green – a systematic review of the state of the art literature”, Journal of Cleaner Production, Vol. 102 No. 1, pp. 18-29. Available at: www.sciencedirect.com/science/article/pii/S0959652615004394

George, M.L. (2002), Lean Six Sigma: Combining Six Sigma Quality with Lean Production Speed, McGraw-Hill, New York, NY.

Ginigaddara, B., Perera, S., Feng, Y. and Rahnamayiezekavat, P. (2022), “An evaluation of off-site construction skill profiles”, Journal of Financial Management of Property and Construction, Vol. 27 No. 1, pp. 16-28, doi: 10.1108/JFMPC-08-2020-0057.

Goh, M. and Goh, Y.M. (2019), “Lean production theory-based simulation of modular construction processes”, Automation in Construction, Vol. 101 No. 1, pp. 227-244. Available at: www.sciencedirect.com/science/article/pii/S092658051730585X

Goodier, C. and Gibb, A. (2007), “Future opportunities for off-site in the UK”, Construction Management and Economics, Vol. 25 No. 6, pp. 585-595, doi: 10.1080/01446190601071821.

Health and Safety Authority (2020), “Annual review of workplace injury, illness and fatality statistics 2018–2019”, available at: www.hsa.ie

Howell, G. and Ballard, G. (1998), “Implementing lean construction: understanding and action”.

Hu, X. and Chong, H.-Y. (2021), “Environmental sustainability of off-site manufacturing: a literature review”, Engineering, Construction and Architectural Management, Vol. 28 No. 1, pp. 332-350, doi: 10.1108/ECAM-06-2019-0288.

Hussin, J.M., Rahman, I.A. and Memon, A.H. (2013), “The way forward in sustainable construction: issues and challenges”, International Journal of Advances in Applied Sciences, Vol. 2 No. 1, pp. 15-24.

Koskela, L., Howell, G., Ballard, G. and Tommelein, I. (2002), “The foundations of lean construction”, Design and Construction: Building in Value, Vol. 291, pp. 211-226.

Lu, W. and Yuan, H. (2011), “A framework for understanding waste management studies in construction”, Waste Management, Vol. 31 No. 6, pp. 1252-1260.

Lucidchart (2022), “What are piping and instrumentation diagrams?”, Lucidchart, available at: www.lucidchart.com/pages/tutorial/p-and-id

Lusardi, M. (2019), “What are process skids? A simple guide for manufacturers”, EPIC Modular Process, available at: www.epicmodularprocess.com/blog/process-skids-benefits

McDermott, O., Antony, J., Sony, M. and Looby, E. (2022b), “A critical evaluation and measurement of organisational readiness and adoption for continuous improvement within a medical device manufacturer”, International Journal of Management Science and Engineering Management, Vol. 24, pp. 1-11, doi: 10.1080/17509653.2022.2073917.

McDermott, O., Antony, J., Bhat, S., Jayaraman, R., Rosa, A., Marolla, G. and Parida, R. (2022a), “Lean six sigma in healthcare: a systematic literature review on motivations and benefits”, Processes, Vol. 10 No. 10.

Mahmood, S., Ahmed, S.M., Panthi, K. and Kureshi, N.I. (2014), “Determining the cost of poor quality and its impact on productivity and profitability”.

Matthew, G.J.W. (2017), “Integrated lean construction and simulation approach to improving on-site modular construction efficiency: a prefabricated and prefinished volumetric construction (PPVC) case study”.

Mostafa, S., Chileshe, N. and Zuo, J. (2014), “A synergistic supply chain enhancing off-site manufacturing uptake in Australian house building”.

Nelson, S., McDermott, O., Woods, B. and Trubetskaya, A. (2022), “An evaluation of lean deployment in Irish micro-enterprises”, Total Quality Management and Business Excellence, Vol. 34 Nos 7-8, pp. 1-20, doi: 10.1080/14783363.2022.2140651.

O’Connor, J., O’Brien, W. and Choi, J. (2016), “Industrial project execution planning: modularization versus stick-built”, Practice Periodical on Structural Design and Construction, Vol. 21 No. 1, p. 04015014.

Olanrewaju, A.L. and Abdul-Aziz, A.-R. (2015), “An overview of the construction industry”, Building Maintenance Processes and Practices, Springer, New York, NY, pp. 9-32.

Pamidimukkala, A. and Kermanshachi, S. (2021), “Impact of covid-19 on field and office workforce in construction industry”, Project Leadership and Society, Vol. 2, pp. 100018-100018.

Peiris, A., Hui, F.K.P., Duffield, C., Wang, J., Garcia, M.G., Chen, Y. and Ngo, T. (2022), “Digitalising modular construction: action research study on manufacturing execution and control (mec) system to enhance off-site manufacturing (osm) productivity”, available at SSRN 4171158.

Peltokorpi, A., Olivieri, H., Granja, A.D. and Seppänen, O. (2018), “Categorizing modularization strategies to achieve various objectives of building investments”, Construction Management and Economics, Vol. 36 No. 1, pp. 32-48, doi: 10.1080/01446193.2017.1353119.

Rahman, A., Gonzalez, V.A. and Amor, R. (2013), “Exploring the synergies between BIM and lean construction to deliver highly integrated sustainable projects”, Proceedings of AUBEA, Auckland, pp. 1-12.

Rosenfeld, Y. (2009), “Cost of quality versus cost of non‐quality in construction: the crucial balance”, Construction Management and Economics, Vol. 27 No. 2, pp. 107-117, doi: 10.1080/01446190802651744.

Sahin, O., Miller, D. and Mohamed, S. (2018), “Value-based modelling: an Australian case of off-site manufactured buildings”, International Journal of Construction Management, Vol. 18 No. 1, pp. 34-52, doi: 10.1080/15623599.2016.1247774.

Sawhney, A., Riley, M. and Irizarry, J. (2020), Construction 4.0: An Innovation Platform for the Built Environment, Routledge, Abingdon, Oxon, available at: www.routledge.com/Construction-40-An-Innovation-Platform-for-the-Built-Environment/Sawhney-Riley-Irizarry/p/book/9780367027308

Snee, R.D. (2010), “Lean six sigma – getting better all the time”, International Journal of Lean Six Sigma, Vol. 1 No. 1, pp. 9-29, doi: 10.1108/20401461011033130.

Spillane, J.P., Oyedele, L.O., Von Meding, J., Konanahalli, A., Jaiyeoba, B.E. and Tijani, I.K. (2011), “Challenges of UK/Irish contractors regarding material management and logistics in confined site construction”, International Journal of Construction Supply Chain Management, Vol. 1 No. 1, pp. 25-42.

Stehn, L. and Höök, M. (2008), “Lean principles in industrialised housing production: the need for a cultural change”, Lean Construction Journal, Vol. 1, pp. 20-33.

Tauriainen, M., Marttinen, P., Dave, B. and Koskela, L. (2016), “The effects of BIM and lean construction on design management practices”, Procedia Engineering, Vol. 164, pp. 567-574.

Tommelein, I.D. (1998), “Pull-driven scheduling for pipe-spool installation: simulation of lean construction technique”, Journal of Construction Engineering and Management, Vol. 124 No. 4, pp. 279-288.

Tortorella, G.L. and Fettermann, D. (2018), “Implementation of industry 4.0 and lean production in Brazilian manufacturing companies”, International Journal of Production Research, Vol. 56 No. 8, pp. 2975-2987, doi: 10.1080/00207543.2017.1391420.

Trenchless (2022), “What is skid? Definition from trenchlesspedia”, available at: www.trenchlesspedia.com/definition/3439/skid

United Nations Environment Programme (2021), “2021 Global status report for buildings and construction | globalabc”, Nairobi, available at: https://globalabc.org/resources/publications/2021-global-status-report-buildings-and-construction

Verrier, B., Rose, B. and Caillaud, E. (2016), “Lean and green strategy: the lean and green house and maturity deployment model”, Journal of Cleaner Production, Vol. 116, pp. 150-156.

Yin, R.K. (2011), Qualitative Research from Start to Finish. Qualitative Research from Start to Finish, The Guilford Press, New York, NY.

Yin, R. (2016), Case Study Research Design and Methods, 5th ed., Sage, Thousand Oaks, CA, available at: https://cjpe.journalhosting.ucalgary.ca/cjpe/index.php/cjpe/article/view/257

Zhang, C., Zayed, T., Hijazi, W. and Alkass, S. (2016), “Quantitative assessment of building constructability using BIM and 4D simulation”, Open Journal of Civil Engineering, Vol. 06 No. 3, pp. 442-461. Available at: www.scirp.org/Journal/Paperabs.aspx?paperid=67232.

Zhang, Y., Lei, Z., Han, S., Bouferguene, A. and Al-Hussein, M. (2020), “Process-oriented framework to improve modular and off-site construction manufacturing performance”, Journal of Construction Engineering and Management, Vol. 146 No. 9, available at: https://ascelibrary.org/doi/10.1061/%28ASCE%29CO.1943-7862.0001909

Zuo, J. and Zhao, Z.-Y. (2014), “Green building research – current status and future agenda: a review”, Renewable and Sustainable Energy Reviews, Vol. 30, pp. 271-281.

Corresponding author

Olivia McDermott can be contacted at: Olivia.McDermott@universityofgalway.ie

Related articles