Challenges of industrial revolution 4.0: quantity surveying students' perspectives

Melissa Li Wen Lim (School of Built Environment, University of Technology Sarawak, Sibu, Malaysia)
Shi Yee Wong (School of Built Environment, University of Technology Sarawak, Sibu, Malaysia)
Chu Sheng Ding (School of Built Environment, University of Technology Sarawak, Sibu, Malaysia)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 10 January 2023

Issue publication date: 10 June 2024

848

Abstract

Purpose

The industrial revolution 4.0 (IR4.0) signifies technological advancements and digitalization. The fragmented and labour-intensive nature of the construction industry inherently possesses difficulties for IR4.0 adoption compared to other industries. This paper aims to investigate the perspectives of quantity surveying students on the challenges of IR4.0 implementation in the construction industry.

Design/methodology/approach

A questionnaire survey were distributed to a population of 191 quantity surveying students, with 96 valid responses returned. Descriptive statistics and factor analysis were employed to analyse the collected data.

Findings

Factor analysis revealed eight components as the key challenges for IR4.0 implementation, which revolved around resistance to change, data security issues, etc.

Practical implications

The findings could provide a guideline to higher education institutions on certain IR4.0-related areas to be incorporated into the syllabus, in ensuring that the students are equipped with such skills and knowledge, in meeting market demands. The construction stakeholders' could look into the identified challenges for strategizing the organizations in moving towards IR4.0 adoption.

Originality/value

To the best of the authors’ knowledge, this is the first study to investigate quantity surveying students' perspectives on the challenges of IR4.0 implementation in the construction industry by employing factor analysis method. The findings contribute to the body of knowledge in relation to the opinions of a younger generation who has more exposure towards technology on the hindrance of IR4.0 adoption.

Keywords

Citation

Lim, M.L.W., Wong, S.Y. and Ding, C.S. (2024), "Challenges of industrial revolution 4.0: quantity surveying students' perspectives", Engineering, Construction and Architectural Management, Vol. 31 No. 6, pp. 2496-2512. https://doi.org/10.1108/ECAM-07-2022-0636

Publisher

:

Emerald Publishing Limited

Copyright © 2022, Emerald Publishing Limited


1. Introduction

The construction industry contributes considerably to a country's gross domestic product (GDP), with 5% in Germany and 7% in Australia, which undoubtedly boosts the employment rate with increased household income (Burda and Severgnini, 2018; Ramasundara et al., 2018). However, the emergence of the fourth industrial revolution (IR4.0) signifies an evolution from mass production to innovative and digitalization production (Schmidt et al., 2015; Zhou et al., 2015), worrying unemployment rate due to the automated operations and replacement of labour force with technologies and/or machines (Birkel et al., 2019; Oesterreich and Teuteberg, 2016). Studies had shown that the evolvement of IR4.0 in the manufacturing sector with the advancement of technologies leads to massive technologies involvement, including the Internet of Things (IoT), augmented reality and big data (Mohamad et al., 2021; Raj et al., 2020). The manufacturing industry had shown a growth of 6.7% in labour productivity per person while only 2.3% for the construction industry (May and Fersht, 2014). This seems to indicate that the late adoption of IR4.0 in the construction industry affecting its productivity. It is undeniable that IR4.0 assists the industry's productivity and overall performance but the associated costs shall not be overlooked (Schmidt et al., 2015; Zhou et al., 2015).

To transform the Malaysian construction industry into a sustainable environment with relevant technologies and high-skilled labour, Strategic Plan 4.0 (2021–2025) was launched by the Construction Industry Development Board (CIDB, 2020). However, this initiative could be considered a laggard if compared to the manufacturing industry as the Ministry of International Trade and Industry (MITI) initiated IR4.0 adoption in 2018, and such initiative gained USD47.6 million (i.e. RM210 million) financial support from the Malaysia government from the year 2019 to 2021 (Ministry of International Trade and Industry, 2018). This seems to indicate the failure of construction stakeholders in identifying the benefits of IR4.0 at the earliest stage, contributing to its late adoption. The management-related stakeholders in the construction industry identified that technologies in IR4.0 assist the growth of the construction industry (Maskuriy et al., 2019). Studies had shown limited research on IR4.0 from construction stakeholders' perspectives.

Multiple stakeholders are involved in the construction industry, and quantity surveyor (QS) could be considered as one of the stakeholders who regularly provides sound advice and actionable feedback to the other stakeholders. As QS involves in construction projects for estimating construction costs prior to the start of the project and monitoring construction expenditures during the construction of a project, QS has to action promptly and timely to avoid time and cost overrun issues (CIDB, 2020). IR4.0 undoubtedly could assist with the efficiency and productivity of construction stakeholders (Dallasega et al., 2018). Hence, identifying the challenges of IR4.0 technologies specifically suited to the construction industry is of utmost importance (Hossain and Nadeem, 2019). With a profound understanding of IR4.0 evolution and implementation, it seems crucial for higher education to introduce IR4.0 at the early stage of quantity surveying education, as this could allow higher institutions to position themselves and prepare future QS that would be able to meet the industrial demand (Tan et al., 2017). Current studies had investigated the drivers of implementing IR4.0 (Demirkesen and Tezel, 2021), challenges faced by the industrial stakeholders (Alaloul et al., 2020; Kasim and Razali, 2021) and the impact of IR4.0 adoptions (Kozlovska et al., 2021), with only one study by Jima'ain et al. (2020) that conducted with students on the challenges from the skill aspects (e.g. communication and networking skill) from four public higher education institutions in West Malaysia.

It is undeniable that higher education plays a pivotal role in educating and shaping the values and areas of expertise of the future generation. Arguably, construction graduates seem not to be fully equipped with construction-related software (Olatunji, 2019). The perspectives of students are essential to assess and measure the existing challenges on IR4.0 implementation in the construction industry as they will be involved in the construction industry in the future. An early identification of the potential challenges perceived by students could allow sufficient knowledge sharing with employers, for better transitioning into the digitalized environment of the construction industry. Therefore, this research aims to investigate the perspective of quantity surveying students on the challenges of IR4.0 implementation.

2. Literature review

The construction industry is labour-intensive and some countries may rely on immigrants for construction activities (Lau et al., 2019b). The classification of construction as one of the riskiest industries (Zid et al., 2020) may alert the stakeholders to a more efficient and safe environment. For example, in 2018, the Malaysian construction industry contributed to 45.5% of the country's fatality rate (Azmi et al., 2020). IR4.0 seems like an opportunity to reduce such a rate with a higher level of technological advancements and involvement, through stakeholders' collaboration in fostering the effectiveness of the construction industry and reducing project completion time (Chen et al., 2018). However, the transition of the construction industry from labour-intensive to technological advancement involves complex issues as stakeholders require financial, skill and time investments and adoptions (de Lange et al., 2017; Lau et al., 2019a). Lau et al. (2019a) accentuated the importance to identify the readiness of construction stakeholders towards transitioning into IR4.0.

Studies had been conducted in different countries on the challenges and strategies of IR4.0 implementation. Osunsanmi et al. (2018) indicated that the financial aspect of new technology investment is the key hindrance to implementation in South Africa despite the potential for time and cost savings. As such, a framework proposed by Dallasega et al. (2018) stressed the influence of IR4.0 on the technological, geographical, organizational and cognitive proximity enablers. Daribay et al. (2019) explored that the globalized standards and community could foster IR4.0 implementation and its competitiveness in Kazakhstan. The UK seems to have sufficient capacity to invest in IR4.0 but is limited by the organizational management system (Newman et al., 2020).

In Malaysia, studies had been conducted mostly in the manufacturing sectors. Lee et al. (2019) found that flexibility is the key challenge of IR4.0 implementation based on experts with more than nine years of experiences. There seems to have a flaw in the Malaysia National Policy on IR4.0 adoption in the manufacturing industry in terms of the scalability manufacturing sector (Ling et al., 2020). Therefore, foreign sectors involvement is essential for knowledge diffusion and awareness towards IR4.0 rules and regulations in ensuring advanced technologies and productivity (Mohamad et al., 2021). To ensure competitiveness, Backhaus and Nadarajah (2019) proposed a conceptual framework to identify the relationship between the productivity of the manufacturing sector and IR4.0. In the construction industry, Aripin et al. (2019) identified implementation cost as the key challenge and cost benefits as the most essential driver for IR4.0 adoption. Alaloul et al. (2020) investigated construction stakeholders' opinions and identified that technical and social factors were the most critical factors. Wee et al. (2022) supported technology deficiency as the most critical challenge. Table 1 showed the challenges identified from the literature review.

As previous research was mostly conducted from the viewpoint of construction stakeholders with limited touch-up on the quantity surveying students' perspective, this study is going to provide empirical data in bridging the knowledge gap. It is vital to study the quantity surveying students as students could have a better grasp on the technology for digitalization evolution. QS, one of the key construction stakeholders, exercises contract practice, project management, construction technologies, cost estimating, project finance and procurement, which required sufficient competencies as indicated by the RICS (2022). Despite the knowledge and skills, RICS emphasizes that QS shall possess good ethical conduct in their practices. This seems to imply that the internationally recognized body affirmed the vital role of QS in the construction industry. Arguably, digitalization in the construction industry shall not diminish QS role and value as errors exist in the digital model and QS shall re-invent and involve in the digital evolution (Olatunji and Akanmu, 2015).

Low et al. (2021) accentuated that educational, government and industry sectors shall collaborate towards IR4.0 evolution. However, the current quantity surveying program offered by the higher education institution faced challenges such as poor Internet connectivity and a lack of skilled lecturers, in assisting students in moving towards digitalization (Babatunde and Ekundayo, 2019). Strategies shall be worked out to solve the problems and ensure students' exposure to digital devices. Therefore, it is important to look into students' perspectives, on the potential challenges of IR4.0 implementation, to enlighten the construction stakeholders on the key aspect to focus on, as well as the educational institution to potentially collaborate with the industry in solving the discovered challenges.

3. Research methodology

This research adopted a quantitative method to investigate the insight of quantity surveying students from a private technical university funded by the state government in Malaysia, on the challenges of IR4.0 implementation in the construction industry. The technical vision and nature of this university are in line with IR4.0 development. This university was chosen as it is located within an economic development corridor established by the Malaysian Government for stimulating investment into the areas and recorded an employment rate of 99.1% for the graduates which assured employability. This seems to assure that the students could share knowledge gained from the university in the workplace to improve industry productivity and efficiency. The university's programme has closely aligned with meeting industrial needs and is accredited by various professional bodies, namely, Board of Quantity Surveyors Malaysia and Pacific Association of Quantity Surveyors.

This research employed a questionnaire survey, as conducted by previous similar studies, such as Alaloul et al. (2020), Contador et al. (2020) and Kumar et al. (2020). Such quantitative research method through a questionnaire survey allows the data to be gathered efficiently, and the quantitative information could be tabulated and quantified in numerical format, for objective representation (Queirós et al., 2017). The questionnaire survey consisted of two parts. Part A seeks for the demographic details of respondents, such as study year, gender and working experiences. Part B intends to collect the opinions of the respondents towards the perceived challenges of IR4.0 implementation in the construction industry, with the adoption of five-point Likert scale of 1 (strongly disagree), 2 (disagree), 3 (neutral), 4 (agree) and 5 (strongly agree).

The questionnaire was designed and distributed to three academicians, three professional QSs and two final-year students for checking the content prior to distributing it to the respondents. The first step of verification occurred with the academicians and QSs who have substantial knowledge of IR4.0 to ensure overall coverage of the challenges and that the wordings used were unambiguous. The second step of verification involved two students to ensure that the students could understand the wording used in the questionnaire. The respondents reported no changes to the questions but some examples were being added at the end of certain terms (Part B) so that the targeted respondents are able to understand the content and answer validly.

An online questionnaire survey was then distributed to a population of 191 Year 1 to Year 4 quantity surveying students, from September to October 2021, through Email and an instant messaging platform (i.e. WhatsApp Messenger). The respondents were followed-up fortnightly. To increase the response rate, the lecturers of this university were approached by the researchers to share the online questionnaire link with their students. The students were invited to participate voluntarily and not coerced. The returned questionnaires were checked to ensure that all questions had been answered without missing data. Responses that were submitted in duplicate had been checked and omitted. This leads to 96 valid responses, representing a response rate of 50.26%.

Descriptive statistics could assess the data collected through quantitative representation (Queirós et al., 2017), while factor analysis could create new concepts and reduce the variables (Cattell, 1988; Malhotra, 2010). Hence, descriptive statistics was adopted for Part A's analysis, representing the background of respondents with percentage, while factor analysis was adopted for Part B's analysis, to generate the most critical challenges from the 37 challenges available, with the assistance of Statistical Package for the Social Sciences (SPSS). This research accepts the challenges with a loading value of more than 0.4 as recommended by Izquierdo Alfaro et al. (2014). Moreover, Varimax rotation was applied to ensure that an equal distribution of variances (Malhotra, 2010).

4. Results and discussions

4.1 Demographic details

Table 2 showed the demographic details of the 96 respondents, with 56.3% of female and 43.8% of male respondents. Majority (74%) of the respondents fall under the age group of 21–25 years old, while only 5.2% of respondents are aged between 26 and 30. This seems to indicate that the respondents are ranging from late Generation Y to earlier/mid-Generation Z. This group of respondents could potentially have the exposure to digital devices since their childhood (Ebbeck et al., 2016), and hence may be considered as the group that may easier in accepting technology changes.

There seems to have an equal spread of respondents in different years of the quantity surveying degree studies with 56.3% of the respondents in the Year 3 and Year 4 studies. This may provide good coverage of the knowledge and perceived uptake of different categories of studies on IR4.0. A majority (69.8%) of the respondents have construction industry working experience and this may indicate that the respondents understand the demands and/or operations of the construction industry.

4.2 Challenges of IR4.0

To ensure that the data obtained are suitable for the factor analysis method, Kaiser–Meyer–Olkin (KMO) and Bartlett's test was conducted. The results showed that the KMO value was 0.748, exceeding the benchmark value of 0.6 (Kaiser, 1974). The Barlett's test of Sphericity achieved 1729.799 chi-square with a statistical significance value of 0.000 met the benchmark of less than 0.05 (Bartlett, 1951). These indicated that the correlation matrix was not an identity matrix and that the collected data was suitable for factor analysis. The factor analysis result showed that 35 of the identified challenges had been loaded into 11 components with Eigenvalue of more than 1, as suggested by Kaiser (1974) and Malhotra (2010). Two identified challenges (V9 and V34) had been eliminated due to the loading factor of less than 0.4. Varimax rotation was conducted on the 35 challenges for equalizing the relative importance of the 11 components, which accounted for 70.191% of the total variance, exceeding the recommended threshold of 60% variance (Malhotra, 2010). Out of the 11 components, three components were removed from analysis due to unrelated challenges or only one challenge being identified (refer to Table 3), which leads to only 8 components with 31 challenges being discussed as follows.

Component 1 consisted of seven underlying challenges and all of the challenges are closely related to the resistance to change caused by the lack of knowledge, company infrastructure and technological concerns, high cost and requirements of skill enhancement. This component accounted for 10.754% variance, which is the largest portion of variance if compared to the other components. The IR4.0-related technologies seem to be uncommon in Malaysia, a developing country, with careful consideration for budget allocations. Demirkesen and Texal (2021) suggested that the reluctance to technology and innovation acceptance contributes towards organizations' resistance to change. The respondents could foresee the resistance to change but younger people could be better at dealing with such challenges and stymie IR4.0 adoption (Czarnitzki and Delanote, 2013). However, organizations may be reluctant to adopt such technologies due to a lack of knowledge on the new technology which demoralizes productivity and original work structure (Newman et al., 2020). Inadequate infrastructure such as high-speed Internet disadvantaged the organization in technology adoption (Raj et al., 2020). The situation is worsened by the high implementation cost and the associated risk (Alaloul et al., 2020). Birkel et al. (2019) supported that the technology introduction in the manufacturing industry is challenged by the scepticism of different parties due to risk uncertainty. Additional costs incurred from providing training for skill enhancement in dealing with both technical and non-technical fundamental knowledge of IR4.0 as well as the external consultancy fee (Ryan and Watson, 2017; Smith, 2014). Anuar and Abidin (2015) further supported that some contractors had limited technology for IR4.0 adoption which resisted them from technological adoption.

Component 2 is related to the challenges caused by data security due to the fragmentation in the construction industry and project complexities, which accounted for 7.459% variance. As the respondents consisted of Generations Y and Z with earlier exposure to technologies, they could potentially be concerned about the effectiveness of data protection and the project information due to the flaws in technologies and complexities of the project. Technological advancement of IR4.0 undoubtedly required a large amount of data flows and this raised concerns about data security (Hecklau et al., 2016). Cyberattacks such as unauthorized files assess prone construction industry towards financial and legal risks (Mantha and de Soto, 2019; Patel and Patel, 2020). Moreover, the fragmented nature of the construction industry and dynamic nature of construction projects created complexity for logical technology adoption, limited knowledge sharing, impeded the effectiveness of communication and hindered innovation (Demirkesen and Tezel, 2021; Lavikka et al., 2018; Yap et al., 2019). Such situation is worsened by the dynamic nature of construction projects which creates uncertainties and complexities for a conducive environment for data sharing (Shen et al., 2010).

Component 3 comprised 7.427% variance, with four key challenges that are closely related to the lack of standardization, and hence this component is named as “lack of standardization created issues on job security, regulatory compliance and low collaboration”. The lack of standardization in the process of information exchange and handling IR4.0 among organizations impeded its adoption among construction stakeholders (Demirkesen and Tezal, 2021). It is undeniable that the adoption of new technology and information sharing needs to comply with the regulations for fairness and legality. However, organizations faced difficulties to comply with the regulations, law and policies while adopting IR4.0 technology (Yu et al., 2017). For instance, Radio-Frequency Identification (RFID) optimizes construction project schedules by digitalizing labour and equipment management and faced issues in complying with the German data protection law for outsourcing data outside European countries (Oesterriech and Teuteberg, 2016). Similar cases could be applicable in Malaysia for organizations to comply with the Personal Data Protection Act (Department of Personal Data Protection, 2010). This appears to indicate the essentiality of collaboration between the academy and industry in fostering comprehensive standard operating procedures for organizations. The management team of the organizations shall comprehend the continuous learning and changes in standardizing organizations towards IR4.0 (Contador et al., 2020). Arguably, the automated process of IR4.0 technologies may create a sense of job insecurity as the employees could perceive employers to reduce the labour force for cost savings measures (Yu et al., 2017; Birkel et al., 2019). Therefore, uniformity and standardization for the standard operating procedure within organizations are essential for transitioning towards digitalization operations (Demirkesen and Tezal, 2021).

Component 4 included four challenges by revealing a phenomenon that legislative uncertainty and improper dispute resolution system could hesitate organizations to invest in the R&D of IR4.0, with 6.865% variance. The students may be exposed to dispute resolution and the changes in legislation throughout their quantity surveying degree and hence could have a better understanding of these terms. Dispute resolution such as the legal court system and alternative dispute resolution aretime-consuming and the new technologies create uncertainties due to the lack of standardized laws and regulations (Li and Yang, 2017). Demirkesen and Tezel (2021) stressed the importance of R&D for the prevailing technological adoption in the construction field, but the investment cost of R&D and its return are questionable. Studies had supported that lack of government mandatory command on the usage of technologies hesitated organizations to adopt appropriate innovations for digitalization (Smith, 2014). This seems to indicate that the certainty in law and regulation and a proper dispute resolution systemcould possibly increase the confidence in stakeholders' involvement with R&D for IR4.0 technologies.

Component 5 consisted of three challenges: “lack of national IR4.0 long-term strategy”, “higher requirement for computing equipment” and “technology changes over time and requires constant updates”, which accounted for 6.652% variance. All these challenges could be summarized as a lack of strategic plan and technology adoption. The national strategic plan is essential to ensure that all stakeholders are aware of the specific IR4.0 objectives of a country as well as the amount of incentives and supports provided by the government. This could help construction companies to plan ahead, investing to upgrade their computing systems and flexibility to update the constant changes of technology. For instance, the French government initiated the cross-cutting “Industrie du Future” to foster digitalization collaboration among organizations for technology implementation and production modernization (Won, 2017; Yang and Gu, 2021). Aripin et al. (2019) accentuated that maintaining technologies on construction sites are inherently difficult due to the dusty and dangerous environment. Hence, a lack of a strategic plan hindered the technological adoption in the construction industry and the additional costs incurred for the continual updates and upgrades of the technologies hesitate the construction stakeholders (de Lange et al., 2017). Therefore, on a fair ground, capturing of the upgrading of technologies associated with appropriate care and environment comes with costs and requires a proper national plan to levy the financial obligations and planning of an organization.

Component 6 detailed issues of intellectual property rights, an unclear vision of digitalization and potential impact on a sustainable environment could lead to a lack of readiness. This component accounted for 6.361% variance. The respondents apprehended that the organization and legislative aspects of the safeguard of intellectual property affect the readiness of stakeholders in adopting IR4.0 (Birkel et al., 2019). The possibility of data being known by the competitors affected organizations' competitive advantage. Moreover, Erol et al. (2016) supported that failure of performing the vision of IR4.0 into practicality affected the supply chain stakeholders' viewpoint on the sustainability of such investment and transformation. Technology involvement such as higher requirements on the computing system and Internet may generate additional waste for machinery or equipment replacement (Birkel et al., 2019) and hence contradicted with the national sustainable development goals.

Component 7 is related to social challenges from the aspects of lack of awareness and labour force, and the threat of new competitors, which accounted for 5.475% variance. The lack of awareness and skilled workers challenged the IR4.0 adoption as the management of organizations may be concerned about its functionality and practicability (Demirkesen and Tezal, 2021). Awareness of the benefits of relevant technologies could reduce cybersecurity attacks and assist employees to support management's decisions in shifting towards digitalization (Cugno et al., 2021; Kumar et al., 2020). However, IR4.0 vanishes the geographical borders that increase competitors from other regions which could affect existing construction organizations' revenue (Birkel et al., 2019; Contador et al., 2020). Muller et al. (2018) confirmed that competitors could offer new platforms and threaten the market share of existing organizations. As such, Anuar and Abidin (2015) supported that an in-depth understanding of IR4.0 is essential for the organizations' adoption yet able to maintain their competitive advantage.

Component 10 revealed that the threat of a new business model may cause by the lack of professional trainers and unclear benefits and gains. This component accounted for 4.686% variance. Birkel et al. (2019) stressed on the organizations' hostility towards a new business model for integrating big data into the platform. However, the existence of a professional trainer could assist with big data integration and troubleshooting. Lack of such trainers affects the organizations' economic confidence in the possible benefits associated with the high-cost investment (Umar, 2021; Arayici and Coates, 2012). Lee and Lee (2015) supported that the unclear benefits and gains hesitated organizations' investment in new technologies. Moreover, construction projects' uncertainties created complexity for the construction stakeholders in estimating the benefits (Lechler et al., 2012), which probably require a professional consultant (e.g. QS) to advise on the associated cost (Olatunji and Akanmu, 2015). Demirkesen and Tezel (2021) added that a complete assessment of the potential benefits was hindered by the fragmented nature of the construction industry, which creates doubt towards the management of organizations for investing in the new business model. It is undeniable that the existing business model seems unable to cater for the digitalization trend (Birkel et al., 2019). Hence, a new business model is essential for organizations to cater the future needs by generating sufficient value from the data, with the assistance of professional trainers.

5. Conclusions

IR4.0 focuses on innovative production and digitalization for improving the efficiency and productivity of the construction industry, but lacking tremendously if compared to other industries. QS who serves as the consultant could potentially advice the construction stakeholders on risk management and mitigation strategies for the technological adoption. Quantity surveying students, the future influencer in the construction industry, could implement the technological usage in the organizations and be the potential earlier trainers to implement IR4.0 technology as they could easily master the technology-related skills. As such, examining the perspective of quantity surveying students on the challenges of IR4.0 adoption could bridge the gap between the expectations of students and the construction stakeholders' expectations.

A questionnaire survey with 37 challenges identified through a comprehensive literature review were distributed to quantity surveying students. The factor analysis results revealed the statistical significance of 31 challenges under 8 components which could offer new insight into bridging the gap between theory and practice. Key issues underlined under the eight components were “resistance to change”, “data security issue”, “lack of standardization”, “legal uncertainty”, “lack of strategic plan and technologies adoption”, “ownership of the intellectual property rights”, “lack of awareness and labour force, and threat of new competitors” and “threat of new business model”. These could possibly be the key focus of construction stakeholders for digitalization transformation by scrutinizing standards for organizations with specific legislative guidance.

These identified challenges could enlighten higher education institutions on the key concerns of students that could possibly be incorporated into the syllabus, to equip their theoretical and practical skills that are necessitates for the IR4.0 technological adoptions. This is one of the first research that gathered the opinions of quantity surveying students and hence could improve the theoretical contribution towards literature. Lecturers could highlight the identified challenges to students for them to have a better transition into labour force in the future. This research not only alert students but industry stakeholders on the emergence and the associated challenges of IR4.0, which could possibly be the pivotal focus for smooth adoption in developing countries. By classifying the challenges, the respective stakeholders could be informed of the underlying challenges of IR4.0 that need to be addressed concurrently. As such, the assessment of the challenges could be conducted for a fruitful IR4.0 adoption and transformation.

Research limitations were identified as the respondents involved only from one university and one programme, which leads to a small sample size. As such, future studies are recommended to employ a wider range of respondents from various higher education institutions for cross-country comparison. Future research could employ qualitative research such as construction industry-based case studies for verifying the identified challenges and developing a comprehensive framework for the collaboration between higher education institutions and construction companies to enhance IR4.0 adoptions.

Challenges identified from literature review

NoTopicsDetailsReferences
1234567891011
1Intellectual property right issueUncertainties on the ownership of information generated
2Lack of dispute resolution systemIncomprehensive resolution system for the additional potential disputes arose
3Legal and contractual uncertaintyUncertainty on the security guideline and responsibilities in shifting information online
4Regulatory complianceDifficulties to decide on the level of accessibility and type of data on cloud that is complied with laws and policies
5Lack of a clear digital operations visionAbsent of managerial long-term vision in investing in IR4.0 technologies
6Inefficient regulatory frameworkLack of mandatory and voluntary framework for organization in adopting IR4.0
7Lack of national IR4.0 long-term strategyAbsent of strategies to enhance IR4.0 in construction industry by Malaysian government
8Low investment in research and development (R&D)Restricted spending in R&D due to low profit margin
9Lack of government supportLack of government assistance such as emphasizes on the networking organizations creation and introduction of technologies
10Hesitation to adoptUncertainties on the return of capital investment hesitated the organizations
11Threat of new business modelHostility of new model for big data integration into the project system
12Unclear benefits and gainsUnknown advantages
13Lack of access to loan/financeLow rate of loans approval for purchasing intellectual technologies
14Organizational and process changeRequirement for re-evaluation of organization structure and business processes
15High implementation costHigh cost of capital investment
16Lack of standardizationLack of standard operating procedures for the transitions of organizations from traditional operations towards digitalization
17Job security issueJob loss due to shifting towards digitalization
18Lack of professional trainerLack of qualified trainer to train existing workers for required skills
19Threat of new competitorsDigitalization reduces entry requirement of new competitors
20Lack of labour forceShortage of labour forces in deploying digital technologies
21Low rate of collaboration between the academy and industryLack of joined collaboration for hypothesis testing and practices
22Resistance to changeConservative nature of construction stakeholders
23Lack of readinessUn-readiness of organizations due to the uncertain risks
24Lack of awarenessLimited awareness on the benefits
25Lack of knowledgeLack of knowledge of organizations on the project operation
26Need for enhanced skillsAdditional training required for IoT skill enhancement
27Threat of new technologyAdoption of new technologies creates distrust among construction stakeholders
28Need to improve company infrastructureUpgrade of Internet and digitalization equipment placing organizations into competitive disadvantages
29Lack of technologyLack of IR4.0-related technologies
30Technology changes over time and has to be updated constantlyChallenge to constantly update the technologies
31Enhancement of existing communication networksExistence of the high-bandwidth network
32Data security and data protectionConcerns on data security
33Higher requirement for computing equipmentConcern on the constant protection on computing equipment on site due to dust and extreme weather
34Negative effect on energy use, global warming, and climate changeIncreasing usage of technologies leads to an increase in greenhouse gases emissions
35The unknown potential impact on sustainability and the environmentReplacement of old machinery with new technologies leads to disposal of materials
36Increase project complexities and uncertaintiesComprehensive specifications of the technologies add burdens to the existing complex projects
37Fragmented and project-based nature of the industryFragmented nature creates difficulties for construction stakeholders to adopt IR4.0 at the similar timing

Demographic details of respondents

CategoriesAspectsPercentage (%)
GenderMale43.8
Female56.3
Age (years old)≤2020.8
21–2574.0
26–305.2
Year of studyYear 121.9
Year 221.9
Year 327.1
Year 429.2
Working experienceYes69.8
No30.2

Factor analysis of the challenges of IR4.0

CodeChallengesLoadingEigenvalueVariance (%)Cumulative variance (%)
Component 1 Challenges of resistance to change which caused by the lack of knowledge, company infrastructure and technological concerns, high cost, and requirements of skill enhancement
V25Lack of knowledge0.7499.73410.75410.754
V22Resistance to change0.681
V28Need to improve company infrastructure0.614
V15High implementation cost0.512
V27Threat of new technology0.506
V29Lack of technology0.477
V26Need for enhanced skills0.463
Component 2 Challenges caused by data security due to the fragmentation of construction industry and project complexities
V37Fragmented and project-based nature of the industry0.7862.7317.45918.214
V36Increase project complexities and uncertainties0.720
V32Data security and data protection0.550
Component 3 Challenges on the lack of standardization created issues on job security, regulatory compliance and low collaboration
V16Lack of standardization0.7672.0687.42725.641
V17Job security issue0.735
V4Regulatory compliance0.505
V21Low rate of collaboration between the academy and industry0.447
Component 4 Legislative uncertainty and improper dispute resolution system, hesitated organizations to invest in research and development
V3Legal and contractual uncertainty0.6981.9106.86532.506
V8Low investment in research and development0.627
V10Hesitation to adopt0.621
V2Lack of dispute resolution system0.584
Component 5 Challenges caused by the lack of strategic plan and technologies adoption
V7Lack of national IR4.0 long-term strategy0.7451.7306.65239.159
V33Higher requirement for computing equipment0.704
V30Technology changes over time and has to be updated constantly0.683
Component 6 Issues of intellectual property rights, unclear vision of digitalization and potential impact on sustainable environment, created unreadiness
V1Intellectual property right issue0.6891.6516.36145.519
V5Lack of a clear digital operations vision0.673
V35The unknown potential impact on sustainability and the environment0.558
V23Lack of readiness0.453
Component 7 Challenges due to lack of awareness and labour force, and threat of new competitors
V19Threat of new competitors0.7491.4205.47550.994
V20Lack of labour force0.668
V24Lack of awareness0.509
Component 8 (excluded due to two unrelated challenges)
V31Enhancement of existing communication networks0.6761.3595.27356.267
V14Organizational and process change0.658
Component 9 (excluded as only one challenge being loaded)
V13Lack of access to loan/finance0.7531.2224.72160.988
Component 10 Threat of new business model due to the lack of professional trainer and unclear benefits and gains
V11Threat of new business model0.8181.1064.68665.674
V18Lack of professional trainer0.499
V12Unclear benefits and gains0.468
Component 11 (excluded as only one challenge being loaded)
V6Inefficient regulatory framework0.7261.0434.51770.191

References

Alaloul, W.S., Liew, M., Zawawi, N.a.W.A. and Kennedy, I.B. (2020), “Industrial Revolution 4.0 in the construction industry: challenges and opportunities for stakeholders”, Ain Shams Engineering Journal, Vol. 11 No. 1, pp. 225-230, doi: 10.1016/j.asej.2019.08.010.

Anuar, K.F. and Abidin, M. (2015), “The challenges in implementing building information model (BIM) for SME’S contractor in the construction industry”, Infrastructure University Kuala Lumpur Research Journal, Vol. 3 No. 1, pp. 40-49.

Arayici, Y. and Coates, P. (2012), “A system engineering perspective to knowledge transfer: a case study approach of BIM adoption”, Virtual Reality–Human Computer Interaction, Vol. 2006, pp. 179-206.

Aripin, I.D.M., Zawawi, E.M.A. and Ismail, Z. (2019), “Factors influencing the implementation of technologies behind industry 4.0 in the Malaysian construction industry”, Matec Web of Conferences, EDP Sciences, 01006.

Azmi, N.S., Sukadarin, E.H. and Aziz, H.A. (2020), “The performance of safety implementation towards accident occurrence in Malaysia construction industry”, Malaysian Journal of Public Health Medicine, Vol. 20 Special1, pp. 14-22.

Babatunde, S.O. and Ekundayo, D. (2019), “Barriers to the incorporation of BIM into quantity surveying undergraduate curriculum in the Nigerian universities”, Journal of Engineering, Design and Technology, Vol. 17 No. 3, pp. 629-648, doi: 10.1108/JEDT-10-2018-0181.

Backhaus, S.K.H. and Nadarajah, D. (2019), “Investigating the relationship between industry 4.0 and productivity: a conceptual framework for Malaysian manufacturing firms”, Procedia Computer Science, Vol. 161, pp. 696-706.

Bartlett, M.S. (1951), “A further note on tests of significance in factor analysis”, British Journal of Psychology, Vol. 4, pp. 1-2.

Birkel, H.S., Veile, J.W., Muller, J., Hartmann, E. and Voigt, K. (2019), “Development of a risk framework for industry 4.0 in the context of sustainability for established manufacturers”, Sustainability, Vol. 11 No. 2, pp. 1-27.

Burda, M.C. and Severgnini, B. (2018), “Total factor productivity convergence in German states since reunification: evidence and explanations”, Journal of Comparative Economics, Vol. 46 No. 1, pp. 192-211.

Cattell, R.B. (1988), “The meaning and strategic use of factor analysis”, in Nesselroade, J.R. and Cattell, R.B. (Eds), Handbook of Multivariate Experimental Psychology. Perspectives on Individual Differences, Springer, Boston, MA. doi: 10.1007/978-1-4613-0893-5_4.

Chen, Q., De Soto, B.G. and Adey, B.T. (2018), “Construction automation: research areas, industry concerns and suggestions for advancement”, Automation in Construction, Vol. 94, pp. 22-38.

[CIDB] Construction Industry Development Board (2020), “Height construction from a new angle: embracing construction revolution”, Construction Industry Development Board, Vol. 3, pp. 1-60.

Contador, J.C., Satyro, W.C., Contador, J.L. and Spinola, M.D.M. (2020), “Flexibility in the Brazilian industry 4.0: challenges and opportunities”, Global Journal of Flexible Systems Management, Vol. 21 No. 1, pp. 15-31.

Cugno, M., Castagnoli, R. and Büchi, G. (2021), “Openness to Industry 4.0 and performance: the impact of barriers and incentives”, Technological Forecasting and Social Change, Vol. 168, 120756.

Czarnitzki, D. and Delanote, J. (2013), “Young innovative companies: the new high-growth firms?”, Industrial and Corporate Change, Vol. 22 No. 5, pp. 1315-1340.

Dallasega, P., Rauch, E. and Linder, C. (2018), “Industry 4.0 as an enabler of proximity for construction supply chains: a systematic literature review”, Computers in Industry, Vol. 99, pp. 205-225.

Daribay, A., Serikova, A. and Ukaegbu, I.A. (2019), “Industry 4.0: Kazakhstani industrialization needs a global perspective”, Procedia Computer Science, Vol. 151, pp. 903-908.

de Lange, P., Bähre, B., Finetti-Imhof, C., Klamma, R., Koch, A. and Oppermann, L. (2017), “Socio-technical challenges in the digital gap between building information modeling and Industry 4.0”, STPIS@ CAiSE, pp. 33-46.

Demirkesen, S. and Tezel, A. (2021), “Investigating major challenges for industry 4.0 adoption among construction companies”, Engineering, Construction and Architectural Management, Vol. 29 No. 3, pp. 1470-1503.

Department of Personal Data Protection (2010), Personal Data Protection Act 2010, Parliament of Malaysia.

Ebbeck, M., Yim, H.Y.B., Chan, Y. and Goh, M. (2016), “Singaporean parents' views of their young children's access and use of technological devices”, Early Childhood Education Journal, Vol. 44 No. 2, pp. 127-134, doi: 10.1007/s10643-015-0695-4.

Erol, S., Schumacher, A. and Sihn, W. (2016), “Strategic guidance towards Industry 4.0–a three-stage process model”, International conference on competitive manufacturing, pp. 495-501.

Gamil, Y. and Rahman, I.A.R. (2019), “Awareness and challenges of building information modelling (BIM) implementation in the Yemen construction industry”, Journal of Engineering and Technology, Vol. 17 No. 5, pp. 1077-1084, doi: 10.1108/JEDT-03-2019-0063.

Hecklau, F., Galeitzke, M., Flachs, S. and Kohl, H. (2016), “Holistic approach for human resource management in Industry 4.0”, Procedia Cirp, Vol. 54, pp. 1-6.

Hossain, M.A. and Nadeem, A. (2019), “Towards digitizing the construction industry: state of the art of construction 4.0”, Proceedings of the ISEC, Vol. 10, pp. 1-6.

Izquierdo Alfaro, I., Olea Díaz, J. and Abad García, F.J. (2014), “Exploratory factor analysis in validation studies: uses and recommendations”, Psicothema, Vol. 26 No. 3, pp. 395-400, doi: 10.7334/psicothema2013.349.

Jima’ain, M.T.A., Hassan, F.N.A., Razak, K.A., Hehsan, A. and Junaidi, J. (2020), “The emerging challenges of Industries Revolution 4.0: a students' perspective”, International Journal of Advanced Science and Technology, Vol. 29 No. 6, pp. 1215-1225.

Kaiser, H.F. (1974), “An index of factorial simplicity”, Psychometrika, Vol. 39, pp. 31-36, doi: 10.1007/BF02291575.

Kasim, N. and Razali, S.A. (2021), “Reinforce technology IR 4.0 implementation for improving safety management in construction site”, International Journal of Sustainable Construction Engineering and Technology, Vol. 12 No. 3, pp. 289-298.

Kozlovska, M., Klosova, D. and Strukova, Z. (2021), “Impact of industry 4.0 platform on the formation of construction 4.0 concept: a literature review”, Sustainability, Vol. 13 No. 5, p. 2683, doi: 10.3390/su13052683.

Kumar, R., Singh, R.K. and Dwivedi, Y.K. (2020), “Application of industry 4.0 technologies in SMEs for ethical and sustainable operations: analysis of challenges”, Journal of Cleaner Production, Vol. 275, 124063, doi: 10.1016/j.jclepro.2020.124063.

Lau, S., Zakaria, R., Aminudin, E., Saar, C.C., Abidin, N., Roslan, A., Abd Hamid, Z., Zain, M.M. and Lou, E. (2019a), “Identification of roadmap of fourth construction industrial revolution”, IOP Conference Series: Materials Science and Engineering, 012029.

Lau, S.E.N., Aminudin, E., Zakaria, R., Saar, C.C., Abidin, N.I., Roslan, A.F., Hamid, Z.A., Zain, M.Z.M., Lou, E. and Shaharuddin, A.B. (2019b), “Revolutionizing the future of the construction industry: strategizing and redefining challenges”, Transactions on the Built Environment 2019, Vol. 192, pp. 105-111, doi: 10.2495/bim190101.

Lavikka, R., Kallio, J., Casey, T. and Airaksinen, M. (2018), “Digital disruption of the AEC industry: technology-oriented scenarios for possible future development paths”, Construction Management and Economics, Vol. 36 No. 11, pp. 635-650.

Lechler, T.G., Edington, B.H. and Gao, T. (2012), “Challenging classic project management: turning project uncertainties into business opportunities”, Project Management Journal, Vol. 43 No. 6, pp. 59-69.

Lee, I. and Lee, K. (2015), “The Internet of things (IoT): applications, investments, and challenges for enterprises”, Business Horizons, Vol. 58 No. 4, pp. 431-440.

Lee, W.Y., Tan, S.T. and Sorooshian, S. (2019), “Impacts of industry 4.0 on Malaysian manufacturing industries”, WSEAS Transactions on Business and Economics, Vol. 16, pp. 355-359.

Li, J. and Yang, H. (2017), “A research on development of construction industrialization based on BIM technology under the background of Industry 4.0”, MATEC Web of Conferences, EDP Sciences, 02046.

Ling, Y.M., Hamid, N.a.A. and Te Chuan, L. (2020), “Is Malaysia ready for Industry 4.0? Issues and challenges in manufacturing industry”, International Journal of Integrated Engineering, Vol. 12 No. 7, pp. 134-150.

Low, S.P., Gao, S. and Ng, E.W.L. (2021), “Future-ready project and facility management graduates in Singapore for industry 4.0: transforming mindsets and competencies”, Engineering, Construction and Architectural Management, Vol. 28 No. 1, pp. 270-290, doi: 10.1108/ECAM-08-2018-0322.

Malhotra, N.K. (2010), Marketing Research: an Applied Orientation, Prentice Hall, Pearson, Englewood Cliffs, NJ.

Mantha, B.R. and de Soto, B.G. (2019), “Cyber security challenges and vulnerability assessment in the construction industry”, Creative Construction Conference, Budapest, June - 2 July 2019.

Maskuriy, R., Selamat, A., Maresova, P., Krejcar, O. and David, O.O. (2019), “Industry 4.0 for the construction industry: review of management perspective”, Economies, Vol. 7 No. 3, p. 68.

May, N. and Fersht, P. (2014), Disrupt or Be Disrupted - the Impact of Digital Technologies on Business Services. A Study of Digital's Impact on Business Services, HfS Research epe, Cambridge.

Ministry of International Trade and Industry (2018), Industry 4WRD National Policy on Industry 4.0, Ministry of International Trade and Industry, Kuala Lumpur.

Mohamad, E., Abd Rahman, M., Rahman, A.A., Mohamad, N., Azlan, N.N. and Saptari, A. (2021), “Investigation of the awareness level in Malaysia's manufacturing industries on the implementation of industry 4.0”, Journal of Industrial Engineering, Vol. 6 No. 1, pp. 53-66.

Muller, J.M., Kiel, D. and Voigt, K. (2018), “What drives the implementation of Industry 4.0? The role of opportunities and challenges in the context of sustainability”, Sustainability, Vol. 10 No. 1, p. 247.

Newman, C., Edwards, D., Martek, I., Lai, J., Thwala, W.D. and Rillie, I. (2020), “Industry 4.0 deployment in the construction industry: a bibliometric literature review and UK-based case study”, Smart and Sustainable Built Environment, Vol. 10 No. 4, pp. 557-580, doi: 10.1108/SASBE-02-2020-0016.

Oesterreich, T.D. and Teuteberg, F. (2016), “Understanding the implications of digitisation and automation in the context of Industry 4.0: a triangulation approach and elements of a research agenda for the construction industry”, Computers in Industry, Vol. 83, pp. 121-139.

Olatunji, O.A. (2019), “Promoting student commitment to BIM in construction education”, Engineering Construction and Architectural Management, Vol. 26 No. 7, pp. 1240-1260.

Olatunji, O.A. and Akanmu, A. (2015), “BIM-FM and consequential loss: how consequential can design model be?”, Built Environment Project and Asset Management, Vol. 5 No. 3, pp. 304-317.

Osunsanmi, T.O., Aigbavboa, C. and Oke, A. (2018), “Construction 4.0: the future of the construction industry in South Africa”, International Journal of Civil and Environmental Engineering, Vol. 12 No. 3, pp. 206-212.

Patel, T. and Patel, V. (2020), “Data privacy in construction industry by privacy-preserving data mining (PPDM) approach”, Asian Journal of Civil Engineering, Vol. 21 No. 3, pp. 505-515.

Queirós, A., Faria, D. and Almeida, F. (2017), “Strengths and limitations of qualitative and quantitative research methods”, European Journal of Education Studies, Vol. 3 No. 9, pp. 369-387, doi: 10.46827/ejes.v0i0.1017.

Raj, A., Dwivedi, G., Sharma, A., De Sousa Jabbour, A.B.L. and Rajak, S. (2020), “Barriers to the adoption of industry 4.0 technologies in the manufacturing sector: an inter-country comparative perspective”, International Journal of Production Economics, Vol. 224, 107546, doi: 10.1016/j.ijpe.2019.107546.

Ramasundara, Y., Johnson, A. and Baumeister, D. (2018), “Australia’s IoT opportunity: driving future growth an ACS report”, ACS, Pricewaterhouse Coopers Consulting, Sydney.

[RICS] Royal Institution of Chartered Surveyors (2022), “RICS requirements and competencies guide”, Royal Institution of Chartered Surveyors, London, available at: https://www.rics.org/globalassets/rics-website/media/qualify/pathway-guides/pathway-guides-requirements-and-competencies.

Ryan, P. and Watson, R. (2017), “Research challenges for the Internet of Things: what role can or play?”, Systems, Vol. 5 No. 1, pp. 1-32.

Schmidt, R., Möhring, M., Härting, R.-C., Reichstein, C., Neumaier, P. and Jozinović, P. (2015), “Industry 4.0-potentials for creating smart products: empirical research results”, International Conference on Business Information Systems, pp. 16-27.

Shen, W., Hao, Q., Mak, H., Neelamkavil, J., Xie, H., Dickinson, J., Thomas, R., Pardasani, A. and Xue, H. (2010), “Systems integration and collaboration in architecture, engineering, construction, and facilities management: a review”, Advanced Engineering Informatics, Vol. 24 No. 2, pp. 196-207.

Smith, P. (2014), “BIM and the 5D project cost manager”, Procedia-Social and Behavioral Sciences, Vol. 119, pp. 465-484.

Tan, A., Udeaja, C., Babatunde, O.S. and Ekundayo, D. (2017), “Sustainable development in a construction related curriculum – quantity surveying students' perspective”, International Journal of Strategic Property Management, Vol. 21 No. 1, pp. 101-113, doi: 10.3846/1648715X.2016.1246387.

Umar, T. (2021), “Challenges of BIM implementation in GCC construction industry”, Engineering, Construction and Architectural Management, Vol. 29 No. 3, pp. 1139-1168, doi: 10.1108/ECAM-11-2019-0608.

Wee, N.Z.Z., Low, W.W., Wong, S.Y. and Wong, K.S. (2022), “Impact of performance and barriers towards industrial revolution 4.0 implementation in Malaysian construction construction projects”, Malaysian Journal of Sustainable Environment, Vol. 9 No. 1, pp. 243-266.

Won, R. (2017), “Industry of the future”, Nature Photonics, Vol. 11 No. 11, pp. 682-683.

Yang, F. and Gu, S. (2021), “Industry 4.0, a revolution that requires technology and national strategies”, Complex Intelligent Systems, Vol. 7, pp. 1311-1325, doi: 10.1007/s40747-020-00267-9.

Yap, J.B.H., Chow, I.N. and Shavarebi, K. (2019), “Criticality of construction industry problems in developing countries: analyzing Malaysian projects”, Journal of Management in Engineering, Vol. 35 No. 5, 04019020.

Yu, Z., Ouyang, J., Li, S. and Peng, X. (2017), “Formal modeling and control of cyber-physical manufacturing systems”, Advances in Mechanical Engineering, Vol. 9 No. 10, pp. 1-12, doi: 10.1177/1687814017725472.

Zhou, K., Liu, T. and Zhou, L. (2015), “Industry 4.0: towards future industrial opportunities and challenges”, 12th International Conference on Fuzzy Systems and Knowledge Discovery (FSKD), Zhangjiajie, China, IEEE, pp. 2147-2152.

Zid, C., Kasim, N., Soomro, A.R. and Laidoune, A. (2020), “The discrepancy in the construction industry of Malaysia: one of the most contributing industries in Malaysia's economy and the highest contributor of the fatal accidents”, IOP Conference Series: Materials Science and Engineering, 012034.

Corresponding author

Shi Yee Wong can be contacted at: wongshiyee@uts.edu.my