To read this content please select one of the options below:

Computing the severities of critical onsite assembly risk factors for modular integrated construction projects

Ibrahim Yahaya Wuni (Department of Building and Real Estate, The Hong Kong Polytechnic University, Kowloon, China)
Geoffrey Qiping Shen (Department of Building and Real Estate, The Hong Kong Polytechnic University, Kowloon, China)
Abdullahi B. Saka (Department of Building and Real Estate, The Hong Kong Polytechnic University, Kowloon, China)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 9 February 2022

Issue publication date: 24 May 2023

782

Abstract

Purpose

Modular integrated construction (MiC) reengineers the traditional construction process. By introducing factory production and onsite assembly (OA) of modules, MiC reinvents construction projects' uncertainties and risk profiles. The OA stage constitutes the highest end of the MiC delivery and supply chains, where several inherited and symbiotic errors and risk events become realities, negatively impacting the MiC project's success. This study explored the severities of OA risk factors for MiC projects.

Design/methodology/approach

A comprehensive literature review, consultation of experts and a questionnaire survey of domain experts were conducted to assess the severity of fifteen OA risk factors for MiC projects. The risk severity index was used to compute and rank the severities of critical OA risk factors for MiC projects, followed by proposed mitigation strategies.

Findings

The study revealed that the top five OA risk factors with the severest impact on MiC projects include modules installation discrepancies and errors, poor cooperation among critical onsite stakeholders, a mismatch between production schedules and site conditions, improper lifting equipment selection for onsite installation and site-fit rework due to discrepancies in drawings.

Originality/value

This study is the first to offer some important insights into the uncertainties that could compromise the OA objectives of MiC projects. It discussed risk management strategies for known and unknown OA risks and made a unique contribution to the theory, practice, and praxis of MiC supply chain risk management.

Keywords

Acknowledgements

This study received full funding from the Research Grants Council, University Grants Committee and The Hong Kong Polytechnic University under the Hong Kong PhD Fellowship Scheme (PF17 - 00649). However, the conclusions made therein are those of the authors and not of the funding bodies.

Citation

Wuni, I.Y., Shen, G.Q. and Saka, A.B. (2023), "Computing the severities of critical onsite assembly risk factors for modular integrated construction projects", Engineering, Construction and Architectural Management, Vol. 30 No. 5, pp. 1864-1882. https://doi.org/10.1108/ECAM-07-2021-0630

Publisher

:

Emerald Publishing Limited

Copyright © 2022, Emerald Publishing Limited

Related articles