Constraints in implementing Public Private Partnership (PPP) in Malaysia

Suhaiza Ismail (Department of Accounting, Faculty of Economics and Management Sciences, International Islamic University Malaysia, Gombak, Malaysia)
Fatimah Azzahra Haris (Department of Accounting, Faculty of Economics and Management Sciences, International Islamic University Malaysia, Gombak, Malaysia)

Built Environment Project and Asset Management

ISSN: 2044-124X

Article publication date: 7 July 2014

1260

Abstract

Purpose

The purpose of this paper is to study two objectives. First, it intends to scrutinize the challenges in implementing Public Private Partnership (PPP) by examining the factors that hinder the successful adoption of PPP in Malaysia. Second, it aims to investigate the differences in the perceptions of the government and the private sector pertaining to the hindrance factors.

Design/methodology/approach

A questionnaire survey was used to elicit the perceptions of the public and private sectors concerning the constraints of PPP implementation in Malaysia. A total of 122 usable responses were obtained, which were analysed using Statistical Package for Social Sciences software. The mean score and mean score ranking were used to examine the importance of the hindrance factors based on the overall responses as well as on the respective responses of the public and the private sectors. An independent sample t-test was used to examine the differences in the perceptions between the two sectors.

Findings

The overall results show that “lengthy delays in negotiation”, “lack of government guidelines and procedures on PPP”, “higher charge to direct users”, “lengthy delays because of political debate” and “confusion over government objectives and evaluation criteria” are the top five constraints for adopting PPP in Malaysia. In terms of the differences in the perceptions between the public and private sector groups, the statistical test results indicate that there are only significant differences in the perceptions for two hindrance factors.

Originality/value

The paper contributes to the existing literature on PPP, which is currently limited, by focusing on the challenges of implementing PPP in a developing country (i.e. Malaysia). More importantly, this paper provides evidence concerning the differences in the opinion of two key players (i.e. the government and the private sector) on the PPP hindrance factors.

Keywords

Citation

Ismail, S. and Azzahra Haris, F. (2014), "Constraints in implementing Public Private Partnership (PPP) in Malaysia", Built Environment Project and Asset Management, Vol. 4 No. 3, pp. 238-250. https://doi.org/10.1108/BEPAM-10-2013-0049

Publisher

:

Emerald Group Publishing Limited

Copyright © 2014, Emerald Group Publishing Limited

Related articles